Environmental Clearance for the proposed stone quarry of Sou. Jagruti Dinesh Mahale located at gut no. 599/1 part, Village Lamkani, Taluka Dhule, District Dhule is an approved mining project in Lamkani, Dhule, Maharashtra. The site covers 2.5 acres.
Who is building it?
The applicant is Jagruti Dinesh Mahale.
Has it been approved?
Yes. Its status is “Environmental approval granted” (since 22 Dec 2025), as of 27 Nov 2026.
Where is it?
In Lamkani, Dhule, Maharashtra.
How big is it?
It has a stated cost of ₹63 lakh and a site of 2.5 acres.
When was it filed?
The application was filed on 14 Jul 2025.
Project details
| Status | Environmental approval granted |
|---|---|
| Status since | 22 Dec 2025 |
| Application filed | 14 Jul 2025 |
| Approval sought | Environmental approval |
| Application type | New project |
| Sector | Mining |
| Applicant | Jagruti Dinesh Mahale |
| Land area | 2.5 acres (1 ha) |
| Project cost | ₹63 lakh |
| Village / locality | Lamkani |
| Taluk / tehsil | Dhule |
| District | Dhule |
| State | Maharashtra |
| Location from | Site boundary on record |
| Our reference | WID-MH-07616 |
In context
44 applications in Dhule since January 2022 are in the same category (Mining): 37 approved, 3 filed or under review, and 4 withdrawn, lapsed or rejected. The approved ones took a median of 35 days from filing to approval. At 2.5 acres, this one is smaller than 100% of them.
No other mining lease on record has applied within 5 km of this site.
Where it is
Lamkani, Dhule, Maharashtra. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.
Other projects nearby
- Proposed Manufacturing Facilities of Nitrate Mixture - Slurry and Emulsion… — returned to applicant, 5.2 km away
- Proposed Manufacturing Facilities of Nitrate Mixture - Slurry and Emulsion… — lapsed, 5.2 km away
- Proposed Manufacturing Facilities of Nitrate Mixture - Slurry and Emulsion… — returned to applicant, 5.2 km away
- Dhule PS – Dhule (BDTCL) 400 kV D/c Line (Quad ACSR/AAAC/AL59 Moose equivalent) — in-principle approval, conditions pending, 10.3 km away
- 220 kV D/C Line from 765 kV AIS Balsane to 220 kV Shivajinagar — more information requested, 11.9 km away
- Environment Clearance for Basalt Stone Mining Project (Area 1.80 ha) at Gut… — environmental approval granted, 16.1 km away
- Diversion of 3.5315 Ha. Forest Land for Proposed 220 KV DC Transmission line… — more information requested, 16.4 km away
- Environmental Clearance for Basalt Stone Mining Project (Area 1.10 ha) at Gut… — environmental approval granted, 16.5 km away
About this information
This page is compiled from publicly available approval records and rewritten in plain language. Statuses can change between our updates, so check with the authority before making decisions. Spotted a mistake? Tell us.