Quick answers
What is this project?
Environmental Clearance for Expansion of the existing Sugar factory from 12,000 TCD to 17,000 TCD, Expansion of Molasses-based Distillery unit from 150 KLPD to 400 KLPD (based on syrup, B-heavy, or C-molasses) by M/s. Shri Ambalika Sugar Private Limited is a proposed industrial project in Baradgaon Sudrik, Karjat, Ahmadnagar, Maharashtra. The site covers 170 acres.
Who is building it?
The applicant is Shri Ambalika Sugar Private Limited.
Has it been approved?
Yes. Its status is “Cleared for impact study” (since 20 Aug 2025), as of 27 Nov 2026.
Where is it?
In Baradgaon Sudrik, Karjat, Ahmadnagar, Maharashtra.
How big is it?
It has a stated cost of ₹1,056.1 crore and a site of 170 acres.
When was it filed?
The application was filed on 18 Aug 2025.
Project details
| Official title | Environmental Clearance for Expansion of the existing Sugar factory from 12,000 TCD to 17,000 TCD, Expansion of Molasses-based Distillery unit from 150 KLPD to 400 KLPD (based on syrup, B-heavy, or C-molasses), along with expansion of the Cogeneration Plant from 38 MW to 62.5 MW at Gat No. 392, Baradgaon Sudrik Village, Ambikanagar, Taluka Karjat, District Ahilyanagar (Ahmednagar), State Maharashtra by M/s. Shri Ambalika Sugar Private Limited. |
|---|---|
| Status | Cleared for impact study |
| Status since | 20 Aug 2025 |
| Application filed | 18 Aug 2025 |
| Approval sought | Environmental approval |
| Application type | Early planning |
| Sector | Industry |
| Applicant | Shri Ambalika Sugar Private Limited |
| Land area | 170 acres (68.8 ha) |
| Project cost | ₹1,056.1 crore |
| Village / locality | Baradgaon Sudrik |
| Taluk / tehsil | Karjat |
| District | Ahmadnagar |
| State | Maharashtra |
| Location from | Site boundary on record |
| Our reference | WID-MH-07895 |
All filings for this project
This project has 2 applications on record. Each is a separate step (an impact study, an approval, an expansion…):
| Filing | Status | Land | Cost |
|---|---|---|---|
| Expansion filed 23 Jan 2026 | More information requested | 170 acres | ₹1,056.1 crore |
| Early planning filed 18 Aug 2025 (this page) | Cleared for impact study | 170 acres | ₹1,056.1 crore |
In context
62 applications in Ahmadnagar since January 2022 are in the same category (Industry): 36 approved, 14 filed or under review, and 12 withdrawn, lapsed or rejected. The approved ones took a median of 2 months from filing to approval. At 170 acres, this one is larger than 73% of them.
3 other applications of any kind have been filed within 5 km of this site since January 2022.
Where it is
Baradgaon Sudrik, Karjat, Ahmadnagar, Maharashtra. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.
Other projects nearby
- Environmental Clearance for Expansion of the existing Sugar factory from… — more information requested, 0 m away
- Application for Amendment in Environmental Clearance for a reduction in the… — environmental approval granted, 0 m away
- Rationalization of Boundaries of Eco-Sensitive Zone around Great Indian… — more information requested, 0 m away
- Modernization cum Capacity Enhancement of the Sugar Plant From 12000 TCD to… — more information requested, 0 m away
- Shri. Viraj Vishwas Maral and Shri. Vinod Vishwas Maral — environmental approval granted, 6 km away
- Shri Suresh Bapurao Saykar,Shri Samir Amrutlal Doshi — environmental approval granted, 6.1 km away
- Yeswadi Stone Quarry by Shri. Machindra Bhimrao Davane — environmental approval granted, 6.3 km away
- Diversion of Forest Land for Laying of Underground Ofc Duct & Cable Within Row… — lapsed, 6.4 km away
More from Shri Ambalika Sugar Private Limited in Ahmadnagar
- Application for Amendment in Environmental Clearance for a reduction in the… — environmental approval granted
- Rationalization of Boundaries of Eco-Sensitive Zone around Great Indian… — more information requested
- Modernization cum Capacity Enhancement of the Sugar Plant From 12000 TCD to… — more information requested
About this information
This page is compiled from publicly available approval records and rewritten in plain language. Statuses can change between our updates, so check with the authority before making decisions. Spotted a mistake? Tell us.