What is this project?
Modernization cum Capacity Enhancement of the Sugar Plant From 12000 TCD to 17000 TCD and Ethanol Plant from 150 KLPD to 400 KLPD (Juice to Ethanol) is a proposed building project in Baradgaon Sudrik, Karjat, Ahmadnagar, Maharashtra. The site covers 168.2 acres.
Who is building it?
The applicant is Shri Ambalika Sugar Private Limited.
Has it been approved?
Not yet. The application is still under review: its status is “More information requested”, as of 27 Nov 2026.
Where is it?
In Baradgaon Sudrik, Karjat, Ahmadnagar, Maharashtra.
How big is it?
It has a stated cost of ₹391.5 crore and a site of 168.2 acres.
When was it filed?
The application was filed on 2 Jul 2024.
Project details
| Official title | Modernization cum Capacity Enhancement of the Sugar Plant From 12000 TCD to 17000 TCD and Ethanol Plant from 150 KLPD to 400 KLPD (Juice to Ethanol) Along with Cogeneration from Existing 38 MW to 66 MW for Shri Ambalika Sugar Pvt. Ltd. at Village- Baradgaon Sudrik Gut no 392B (Old S. No. 123), Taluka Karjat, District Ahmednagar in the state of Maharashtra. |
|---|---|
| Status | More information requested |
| Status since | 2 Jul 2024 |
| Application filed | 2 Jul 2024 |
| Approval sought | Wildlife review |
| Application type | New project |
| Sector | Buildings & townships |
| Applicant | Shri Ambalika Sugar Private Limited |
| Land area | 168.2 acres (68.1 ha) |
| Project cost | ₹391.5 crore |
| Village / locality | Baradgaon Sudrik |
| Taluk / tehsil | Karjat |
| District | Ahmadnagar |
| State | Maharashtra |
| Location from | Site boundary on record |
| Our reference | WID-MH-16477 |
In context
74 applications in Ahmadnagar since January 2022 are in the same category (Buildings & townships): 16 approved, 51 filed or under review, and 7 withdrawn, lapsed or rejected. The approved ones took a median of 4 months from filing to approval. At 168.2 acres, this one is larger than 84% of them.
4 other applications of any kind have been filed within 5 km of this site since January 2022.
Where it is
Baradgaon Sudrik, Karjat, Ahmadnagar, Maharashtra. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.
Other projects nearby
- Rationalization of Boundaries of Eco-Sensitive Zone around Great Indian… — more information requested, 0 m away
- Application for Amendment in Environmental Clearance for a reduction in the… — environmental approval granted, 0 m away
- Environmental Clearance for Expansion of the existing Sugar factory from… — more information requested, 0 m away
- Environmental Clearance for Expansion of the existing Sugar factory from… — cleared for impact study, 0 m away
- Shri. Viraj Vishwas Maral and Shri. Vinod Vishwas Maral — environmental approval granted, 6 km away
- Shri Suresh Bapurao Saykar,Shri Samir Amrutlal Doshi — environmental approval granted, 6.1 km away
- Yeswadi Stone Quarry by Shri. Machindra Bhimrao Davane — environmental approval granted, 6.3 km away
- Diversion of Forest Land for Laying of Underground Ofc Duct & Cable Within Row… — lapsed, 6.4 km away
More from Shri Ambalika Sugar Private Limited in Ahmadnagar
- Environmental Clearance for Expansion of the existing Sugar factory from… — more information requested
- Environmental Clearance for Expansion of the existing Sugar factory from… — cleared for impact study
- Application for Amendment in Environmental Clearance for a reduction in the… — environmental approval granted
- Rationalization of Boundaries of Eco-Sensitive Zone around Great Indian… — more information requested
About this information
This page is compiled from publicly available approval records and rewritten in plain language. Statuses can change between our updates, so check with the authority before making decisions. Spotted a mistake? Tell us.