Quick answers
What is PEN Off-Stream Closed Loop Pumped Storage Project?
PEN Off-Stream Closed Loop Pumped Storage Project is a proposed water and irrigation project in Jirne, Pen, Raigarh, Maharashtra. The site covers 2,295.5 acres.
Who is building it?
The applicant is Torrent Energy Storage Solutions Private Limited.
Has it been approved?
Not yet. The application is still under review: its status is “Under environmental review”, as of 27 Nov 2026.
Where is it?
In Jirne, Pen, Raigarh, Maharashtra.
How big is it?
It has a stated cost of ₹9,858.8 crore and a site of 2,295.5 acres.
When was it filed?
The application was filed on 17 Jul 2026.
Project details
| Status | Under environmental review |
|---|---|
| Status since | 15 Sept 2026 |
| Application filed | 17 Jul 2026 |
| Approval sought | Environmental approval |
| Application type | Early planning |
| Sector | Water & irrigation |
| Applicant | Torrent Energy Storage Solutions Private Limited |
| Land area | 2,295.5 acres (929 ha) |
| Project cost | ₹9,858.8 crore |
| Village / locality | Jirne |
| Taluk / tehsil | Pen |
| District | Raigarh |
| State | Maharashtra |
| Location from | Site boundary on record |
| Our reference | WID-MH-12066 |
In context
31 applications in Raigarh since January 2022 are in the same category (Water & irrigation): 11 approved, 14 filed or under review, and 6 withdrawn, lapsed or rejected. The approved ones took a median of 2 months from filing to approval. At 2,295.5 acres, this one is larger than 67% of them.
2 other applications of any kind have been filed within 5 km of this site since January 2022.
Where it is
Jirne, Pen, Raigarh, Maharashtra. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.
Other projects nearby
- Proposed 400/220 KV MC Line from Existing 400 KV DC Padagaon to Nagothane Line… — under forest review, 4.3 km away
- Proposed 400/220 KV MC Line from Existing 400 KV DC Padgha to Nagothane Line… — more information requested, 4.3 km away
- Proposed units for manufacture of Polyvinyl Chloride (15,00,000 TPA) and Vinyl… — cleared for impact study, 7.4 km away
- Transfer of EC No. EC24A2101MH5198333N, dated 30-04-2025 granted to Reliance… — environmental approval granted, 7.6 km away
- Transfer of EC No. EC24A2101MH5198333N, dated 30-04-2025 granted to Reliance… — lapsed, 7.6 km away
- Proposed units for manufacture of Polyvinyl Chloride (15,00,000 TPA) and Vinyl… — environmental approval granted, 7.6 km away
- Amendment in Ec Granted Vide File No. J-11011/177/2015-Ia-Ii(I), Dated… — environmental approval granted, 7.6 km away
- Proposed expansion in Gas Cracker Unit (Ethylene - 3,50,000 TPA) by Reliance… — environmental approval granted, 7.7 km away
More from Torrent Energy Storage Solutions Private Limited in Raigarh
- Saidongar-1 Karjat (3000 MW) Off-stream Open Loop Pumped Storage Project — under forest review
- Saidongar 1 - Karjat Pumped Storage Project — environmental approval granted
- Saidongar 1 - Karjat Pumped Storage Project — environmental approval granted
- Saidongar-1 Karjat (3000 MW) Off-stream Open Loop Pumped Storage Project — forest land use approved
- Saidongar 1 - Karjat Pumped Storage Project — cleared for impact study
6 Torrent Energy Storage projects in Raigarh
All 7 Torrent Energy Storage projects across India
About this information
This page is compiled from publicly available approval records and rewritten in plain language. Statuses can change between our updates, so check with the authority before making decisions. Spotted a mistake? Tell us.