What is Developing? Open the mapMap

Cleared for impact studyIndustry · Nagpur, Maharashtra

Proposed Expansion of Grain based Distillery plant from 60 KLPD (Ethanol) to 75KLPD (RS/ENA/Ethanol) & Cogeneration Power Plant from 1.5 MWh to 2.0 MWh at Bothali Rithi, Tal: Mohadi, Dist.: Bhandara, Maharashtra State by M/s Tajshree Biofuel Private Limited.

Proposed Expansion of Grain based Distillery plant from 60 KLPD (Ethanol) to 75KLPD (RS/ENA/Ethanol) & Cogeneration Power Plant from 1.5 MWh to 2.0 MWh at Bothali Rithi, Tal: Mohadi, Dist.: Bhandara, Maharashtra State by M/s Tajshree Biofuel Private Limited is a proposed industrial project in Adegaon, Mauda, Nagpur, Maharashtra. The site covers 14.9 acres. Its stated project cost is ₹95 crore. As of 27 Nov 2026, its status is “Cleared for impact study” (since 20 May 2026).

See it on the live map All projects in Nagpur

Data last refreshed 27 Nov 2026, 6:36 am IST. We check for new filings and status changes twice a day.

Quick answers

What is this project?

Proposed Expansion of Grain based Distillery plant from 60 KLPD (Ethanol) to 75KLPD (RS/ENA/Ethanol) & Cogeneration Power Plant from 1.5 MWh to 2.0 MWh at Bothali Rithi, Tal: Mohadi, Dist.: Bhandara, Maharashtra State by M/s Tajshree Biofuel Private Limited is a proposed industrial project in Adegaon, Mauda, Nagpur, Maharashtra. The site covers 14.9 acres.

Who is building it?

The applicant is Tajshree Biofuel Private Limited.

Has it been approved?

Yes. Its status is “Cleared for impact study” (since 20 May 2026), as of 27 Nov 2026.

Where is it?

In Adegaon, Mauda, Nagpur, Maharashtra.

How big is it?

It has a stated cost of ₹95 crore and a site of 14.9 acres.

When was it filed?

The application was filed on 9 Apr 2026.

Project details

StatusCleared for impact study
Status since20 May 2026
Application filed9 Apr 2026
Approval soughtEnvironmental approval
Application typeEarly planning
SectorIndustry
ApplicantTajshree Biofuel Private Limited
Land area14.9 acres (6 ha)
Project cost₹95 crore
Village / localityAdegaon
Taluk / tehsilMauda
DistrictNagpur
StateMaharashtra
Location fromSite boundary on record
Our referenceWID-MH-12487

In context

79 applications in Nagpur since January 2022 are in the same category (Industry): 51 approved, 13 filed or under review, and 15 withdrawn, lapsed or rejected. The approved ones took a median of 43 days from filing to approval. At 14.9 acres, this one is smaller than 53% of them.

Where it is

Adegaon, Mauda, Nagpur, Maharashtra. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.

Other projects nearby

All 5 Tajshree Biofuel projects across India

About this information

This page is compiled from publicly available approval records and rewritten in plain language. Statuses can change between our updates, so check with the authority before making decisions. Spotted a mistake? Tell us.