One of 2 filings for this project. The project's main page, with every filing and where each stands: Proposed Manufacturing Unit of Fruit Base Distillery Plant by M/s. Rajdheer Wine Pvt. Ltd
Project details
| Official title | Proposed Manufacturing Unit of Fruit Base Distillery Plant along with Grapes Winery to Produce 5 KLD Spirit and 30 KLD Wine, located at Gat. No.: 22/1/A/1, 22/2, Village: Bhilwad, Post: Kapshi, Taluka: Deola, District: Nashik, Maharashtra by M/s. Rajdheer Wine Pvt. Ltd. |
|---|---|
| Status | Returned to applicant |
| Status since | 11 Aug 2026 |
| Application filed | 11 Jul 2026 |
| Approval sought | Environmental approval |
| Application type | New project |
| Sector | Industry |
| Applicant | Rajdheer Wine Pvt Ltd |
| Land area | 3.7 acres (1.5 ha) |
| Project cost | ₹6 crore |
| Village / locality | Bhilwad |
| Taluk / tehsil | Deola |
| District | Nashik |
| State | Maharashtra |
| Location from | Site boundary on record |
| Our reference | WID-MH-12583 |
All filings for this project
This project has 2 applications on record. Each is a separate step (an impact study, an approval, an expansion…):
| Filing | Status | Land | Cost |
|---|---|---|---|
| New project filed 11 Jul 2026 (this page) | Returned to applicant | 3.7 acres | ₹6 crore |
| Early planning filed 3 Dec 2025 | Cleared for impact study | 3.7 acres | ₹6 crore |
In context
63 applications in Nashik since January 2022 are in the same category (Industry): 43 approved, 11 filed or under review, and 9 withdrawn, lapsed or rejected. The approved ones took a median of 2 months from filing to approval. At 3.7 acres, this one is smaller than 59% of them.
2 other applications of any kind have been filed within 5 km of this site since January 2022.
Where it is
Bhilwad, Deola, Nashik, Maharashtra. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.
Other projects nearby
- Proposed Manufacturing Unit of Fruit Base Distillery Plant by M/s. Rajdheer… — cleared for impact study, 0 m away
- Proposed Manufacturing Unit of Fruit Base Distillery Plant — environmental approval granted, 100 m away
- Proposed Manufacturing Unit of Fruit Base Distillery Plant — cleared for impact study, 100 m away
- Environmental Clearance for Basalt Stone Mining Project (Area 1.20 ha) — environmental approval granted, 5.5 km away
- Environmental Clearance for Basalt Stone Mining Project (Area 1.10 ha) — environmental approval granted, 9.9 km away
- Environment Clearance for Basalt Stone Mining Project (Area 1.14 ha) at Gut… — environmental approval granted, 11.7 km away
- Environmental Clearance for proposed Vithewadi Sawaki Sand Ghat (2.75 ha) At… — environmental approval granted, 12.3 km away
- Transfer of Environmental Clearance of Lohner 1 Sandghat, Gut No. 955, 956,… — environmental approval granted, 12.6 km away
About this information
This page is compiled from publicly available approval records and rewritten in plain language. Statuses can change between our updates, so check with the authority before making decisions. Spotted a mistake? Tell us.