Diversion of 36.25 Ha. Forest Land for Integrated Steel Plant of 25.0 Mtpa Capacity With Captive Power Plant, Cement Plant, and Allied Facilities

Diversion of 36.25 Ha. Forest Land for Integrated Steel Plant of 25.0 Mtpa Capacity With Captive Power Plant, Cement Plant, and Allied Facilities is a proposed industrial project in Bhendala, Chamorshi, Gadchiroli, Maharashtra. The site covers 9,277.1 acres. Its stated project cost is ₹1,000 crore. As of 27 Nov 2026, its status is “Under forest review” (since 9 Jul 2026).

See it on the live map All projects in Gadchiroli

Data last refreshed 27 Nov 2026, 6:36 am IST. We check for new filings and status changes twice a day.

Quick answers

What is this project?

Diversion of 36.25 Ha. Forest Land for Integrated Steel Plant of 25.0 Mtpa Capacity With Captive Power Plant, Cement Plant, and Allied Facilities is a proposed industrial project in Bhendala, Chamorshi, Gadchiroli, Maharashtra. The site covers 9,277.1 acres.

Who is building it?

The applicant is Maharashtra Industrial Development Corporation.

Has it been approved?

Not yet. The application is still under review: its status is “Under forest review”, as of 27 Nov 2026.

Where is it?

In Bhendala, Chamorshi, Gadchiroli, Maharashtra.

How big is it?

It has a stated cost of ₹1,000 crore; a site of 9,277.1 acres and 90 acres (36.4 ha) of forest land.

When was it filed?

The application was filed on 30 Jun 2026.

Project details

Official titleProposal for Diversion of 36.25 Ha. Forest Land for Integrated Steel Plant of 25.0 Mtpa Capacity With Captive Power Plant, Cement Plant, and Allied Facilities at Village Ghargao, Ramala, Phokurdi, Dotkuli, Khandala, Bhendala, Wagholi, Saganapur, Weltur (Reeth), Kanholi, Navgaon, Chakalpeth, Mohurli, Mokasa, Pharada, Chamorshi, District Gadchiroli, Maharashtra.
StatusUnder forest review
Status since9 Jul 2026
Application filed30 Jun 2026
Approval soughtForest land use
Application typeNew project
SectorIndustry
ApplicantMaharashtra Industrial Development Corporation
Land area9,277.1 acres (3,754.3 ha)
Forest land90 acres (36.4 ha)
Project cost₹1,000 crore
Village / localityBhendala
Taluk / tehsilChamorshi
DistrictGadchiroli
StateMaharashtra
Location fromSite boundary on record
Our referenceWID-MH-14920

In context

30 applications in Gadchiroli since January 2022 are in the same category (Industry): 15 approved, 9 filed or under review, and 6 withdrawn, lapsed or rejected. The approved ones took a median of 2 months from filing to approval. At 9,277.1 acres, this one is larger than 97% of them.

6 other applications of any kind have been filed within 5 km of this site since January 2022.

Where it is

Bhendala, Chamorshi, Gadchiroli, Maharashtra. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.

Other projects nearby

More from Maharashtra Industrial Development Corporation in Gadchiroli

All 33 Maharashtra Industrial Development Corporation projects across India

About this information

This page is compiled from publicly available approval records and rewritten in plain language. Statuses can change between our updates, so check with the authority before making decisions. Spotted a mistake? Tell us.