| Official title | Proposal for Diversion of Forest Land for Construction of "LILO of Narendra (New)- Pune (GIS) 765 KV D/C Transmission line (CKT#1 and CKT#2) and LILO of Hinjewadi- Koyna 400KV Transmission line at 765/400KV Pune-III GIS Substation by Pune-III Transmission Ltd (P3TL) |
|---|---|
| Status | More information requested |
| Status since | 28 Jul 2026 |
| Application filed | 27 Jul 2025 |
| Approval sought | Forest land use |
| Application type | New project |
| Sector | Power |
| Applicant | Pune-Iii Transmission Limited |
| Land area | 11,915.7 acres (4,822.1 ha) |
| Forest land | 71.1 acres (28.8 ha) |
| Project cost | ₹302 crore |
| Village / locality | Bhongvali |
| Taluk / tehsil | Bhor |
| District | Pune |
| State | Maharashtra |
| Location from | Site boundary on record |
| Our reference | WID-MH-15022 |
In context
16 applications in Pune since January 2022 are in the same category (Power): 0 approved, 4 filed or under review, and 12 withdrawn, lapsed or rejected. At 11,915.7 acres, this one is larger than 83% of them.
4 other applications of any kind have been filed within 5 km of this site since January 2022.
Where it is
Bhongvali, Bhor, Pune, Maharashtra. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.
Other projects nearby
- Proposed Defense Manufacturing Facility located at Plot No. F – 4, Additional… — environmental approval granted, 4 km away
- Proposed Synthetic Organic Chemicals- Active Pharmaceutical Ingredients (API)… — environmental approval granted, 4.9 km away
- Proposed Synthetic Organic Chemicals- Active Pharmaceutical Ingredients (API)… — cleared for impact study, 4.9 km away
- Proposed Synthetic Organic Chemicals- Active Pharmaceutical Ingredients (API)… — lapsed, 4.9 km away
- Proposed Expansion in the Manufacturing of Carbon and Alloy Steel Cast Blooms… — more information requested, 5.8 km away
- Proposed Expansion in the Manufacturing of Carbon and Alloy Steel Cast Blooms… — returned to applicant, 5.8 km away
- Environmental Clearance for Basalt Stone Quarry of Shri. Dipak Gahininath… — environmental approval granted, 5.9 km away
- Shri. Dinesh Shashikant Bhintade & Shri. Namdev b Dattatray Samgir — not approved, 6.1 km away
About this information
This page is compiled from publicly available approval records and rewritten in plain language. Statuses can change between our updates, so check with the authority before making decisions. Spotted a mistake? Tell us.