Project details
| Official title | Proposed Expansion in the Manufacturing of Carbon and Alloy Steel Cast Blooms from 1,80,000 TPA to 3,00,000 TPA by Upgradation and Modernization of Existing facilities at Village- Kolvihre, Jejuri- Morgaon Road, Taluka- Purandar, District- Pune, Maharashtra by Kirloskar Ferrous Industries Limited |
|---|---|
| Status | More information requested |
| Status since | 4 Nov 2026 |
| Application filed | 14 Oct 2026 |
| Approval sought | Environmental approval |
| Application type | Early planning |
| Sector | Industry |
| Applicant | Kirloskar Ferrous Industries LTD |
| Land area | 201.4 acres (81.5 ha) |
| Project cost | ₹999.5 crore |
| Village / locality | Kolvihire |
| Taluk / tehsil | Purandhar |
| District | Pune |
| State | Maharashtra |
| Location from | Site boundary on record |
| Our reference | WID-MH-12231 |
All filings for this project
This project has 2 applications on record. Each is a separate step (an impact study, an approval, an expansion…):
| Filing | Status | Land | Cost |
|---|---|---|---|
| Early planning filed 14 Oct 2026 (this page) | More information requested | 201.4 acres | ₹999.5 crore |
| Early planning filed 16 May 2026 | Returned to applicant | 201.4 acres | ₹999.5 crore |
In context
121 applications in Pune since January 2022 are in the same category (Industry): 81 approved, 22 filed or under review, and 18 withdrawn, lapsed or rejected. The approved ones took a median of 2 months from filing to approval. At 201.4 acres, this one is larger than 97% of them.
7 other applications of any kind have been filed within 5 km of this site since January 2022.
Where it is
Kolvihire, Purandhar, Pune, Maharashtra. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.
Other projects nearby
- Proposed Expansion in the Manufacturing of Carbon and Alloy Steel Cast Blooms… — returned to applicant, 0 m away
- Proposed Defense Manufacturing Facility located at Plot No. F – 4, Additional… — environmental approval granted, 2.8 km away
- Proposed Synthetic Organic Chemicals- Active Pharmaceutical Ingredients (API)… — environmental approval granted, 3 km away
- Proposed Synthetic Organic Chemicals- Active Pharmaceutical Ingredients (API)… — cleared for impact study, 3 km away
- Proposed Synthetic Organic Chemicals- Active Pharmaceutical Ingredients (API)… — lapsed, 3.2 km away
- 6 - MW Solar Plant MSKVY 2.0 at kalewadi (33/11 KV Deulgaon Substation) — lapsed, 4.5 km away
- 5-MW Solar Plant MSKVY 2.0 at Kothale — lapsed, 4.5 km away
- Diversion of Forest Land for Construction of "LILO of Narendra (New)- Pune… — more information requested, 5.8 km away
All 14 Kirloskar Ferrous Industries projects across India
About this information
This page is compiled from publicly available approval records and rewritten in plain language. Statuses can change between our updates, so check with the authority before making decisions. Spotted a mistake? Tell us.