What is this project?
Diversion of 2.640 Ha. Rf Land for Construction of 220KV Transmission Line From 220KV Gadchandur Sub Station to M/S. Dalmia Cement (Bharat)ltd, Naranda is a proposed power project in Naranda, Korpana, Chandrapur, Maharashtra. The site covers 88.3 acres.
Who is building it?
The applicant is Msetcl Ehv Projects Division Chandrapur.
Has it been approved?
Not yet. The application is still under review: its status is “In-principle approval, conditions pending”, as of 27 Nov 2026.
Where is it?
In Naranda, Korpana, Chandrapur, Maharashtra.
How big is it?
It has a stated cost of ₹66 lakh; a site of 88.3 acres and 6.5 acres (2.6 ha) of forest land.
When was it filed?
The application was filed on 28 Aug 2023.
Project details
| Status | In-principle approval, conditions pending |
|---|---|
| Status since | 15 Sept 2025 |
| Application filed | 28 Aug 2023 |
| Approval sought | Forest land use |
| Application type | New project |
| Sector | Power |
| Applicant | Msetcl Ehv Projects Division Chandrapur |
| Land area | 88.3 acres (35.7 ha) |
| Forest land | 6.5 acres (2.6 ha) |
| Project cost | ₹66 lakh |
| Village / locality | Naranda |
| Taluk / tehsil | Korpana |
| District | Chandrapur |
| State | Maharashtra |
| Location from | Site area on record |
| Our reference | WID-MH-15411 |
In context
10 applications in Chandrapur since January 2022 are in the same category (Power): 1 approved, 7 filed or under review, and 2 withdrawn, lapsed or rejected. At 88.3 acres, this one is smaller than 80% of them.
8 other applications of any kind have been filed within 5 km of this site since January 2022.
Where it is
Naranda, Korpana, Chandrapur, Maharashtra. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.
Other projects nearby
- Preliminary Exploration for locating Limestone deposits in Naranda-Bori… — initial checks, 150 m away
- Preliminary Exploration for locating Limestone deposits in Naranda-Bori… — lapsed, 150 m away
- Diversion of 17.00 Ha. Forest land for Mining lease of Naranda Limestone Block… — more information requested, 2.1 km away
- Ec Amendment of Naranda Limestone Mine (Ml Area 71.01 Ha and Production of 2.4… — lapsed, 2.5 km away
- Naranda Limestone Mines ML area 71.01 ha and Production of 2.4 MTPA — environmental approval granted, 2.5 km away
- Wanoja Limestone Block (Area: 313 Ha) with Cement Grade Limestone Production… — cleared for impact study, 3.7 km away
- Wanoja Limestone Block (area 313 Ha.) in Villages- Wanoja, Zutting and… — returned to applicant, 3.7 km away
- Zutting(18.06 Ha), Zutting(25.28 Ha), Zutting(42.16 Ha) Limestone Mines — under environmental review, 4.7 km away
More from Msetcl Ehv Projects Division Chandrapur in Chandrapur
- Diversion of Forest Land Over 74.015 Ha for Laying 400 KV Transmission Line — under forest review
- 132 KV DC Mul -SICOM Chandrapur Transmission line. — under wildlife review
3 Msetcl Ehv Projects projects in Chandrapur
All 5 Msetcl Ehv Projects projects across India