Project details
| Status | In-principle approval, conditions pending |
|---|---|
| Status since | 2 Sept 2026 |
| Application filed | 30 Mar 2026 |
| Approval sought | Forest land use |
| Application type | New project |
| Sector | Power |
| Applicant | Mahatransco |
| Land area | 3,795.5 acres (1,536 ha) |
| Forest land | 9.7 acres (3.9 ha) |
| Project cost | ₹32.3 crore |
| Village / locality | Ambesari |
| Taluk / tehsil | Dahanu |
| District | Palghar |
| State | Maharashtra |
| Location from | Site boundary on record |
| Our reference | WID-MH-15608 |
In context
23 applications in Palghar since January 2022 are in the same category (Power): 5 approved, 13 filed or under review, and 5 withdrawn, lapsed or rejected. At 3,795.5 acres, this one is larger than 77% of them.
1 other applications of any kind have been filed within 5 km of this site since January 2022.
Where it is
Ambesari, Dahanu, Palghar, Maharashtra. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.
Other projects nearby
- MahaNet-I(BharatNet-II)-Palghar-Dahanu-Application-1 — lapsed, 5 km away
- 132KV DAHANU-AMBESARI TRANSMISSION LINE FOR ESTABLISHMENT OF PROPOSED NHSRCL'S… — coastal clearance granted, 6.6 km away
- Vadhavan Port Water Supply Scheme, Taluka – Dahanu, District – Palghar by… — more information requested, 6.7 km away
- Diversion of 2.2950 Ha. Forest Land for Proposed 132 KV DCMC line from LILO on… — in-principle approval, conditions pending, 7.2 km away
- Mumbai Ahmedabad High Speed Rail Project — forest land use approved, 7.8 km away
- DIVERSION OF 44.2368 Ha. FOREST LAND FOR CONSTRUCTION OF 132 KV DC LINE FROM… — lapsed, 8.8 km away
- Diversion and Confirmation for Restoration Order [section 3(2)] and Management… — not approved, 9.4 km away
- Proposed Residential Bungalow Scheme — lapsed, 9.6 km away
More from Mahatransco in Palghar
- Diversion of 1.7080 Ha. Forest Land for Proposed Construction 220 KV PG-Manor… — more information requested
- "Lilo on Existing 220kv Boisar (PGCIL) – Vasai Line at 220kv Chikhaldongri… — under forest review
- Diversion of 2.2950 Ha. Forest Land for Proposed 132 KV DCMC line from LILO on… — in-principle approval, conditions pending
- LILO on existing 220 kV Boisar (PGCIL)-Vasai Line at 220 kV Chikhaldongari… — coastal clearance granted
- 132KV DAHANU-AMBESARI TRANSMISSION LINE FOR ESTABLISHMENT OF PROPOSED NHSRCL'S… — coastal clearance granted
- 132 KV DCDC line from 132 KV Dahanu substation to 132 KV Suryanagar substation… — coastal clearance granted
About this information
This page is compiled from publicly available approval records and rewritten in plain language. Statuses can change between our updates, so check with the authority before making decisions. Spotted a mistake? Tell us.