One of 2 filings for this project. The project's main page, with every filing and where each stands: "New EMU Carshed cum POH Workshop" at Vangaon on Western Railway under MUTP- 3A-II,…
Project details
| Status | More information requested |
|---|---|
| Status since | 1 Mar 2025 |
| Application filed | 8 Nov 2023 |
| Approval sought | Forest land use |
| Application type | New project |
| Sector | Railways & metro |
| Applicant | Mumbai Railway Vikas Corporation Limited |
| Land area | 107.9 acres (43.7 ha) |
| Forest land | 92.6 acres (37.5 ha) |
| Project cost | ₹1,200 crore |
| Village / locality | Asangaon |
| Taluk / tehsil | Dahanu |
| District | Palghar |
| State | Maharashtra |
| Location from | Site boundary on record |
| Our reference | WID-MH-15914 |
All filings for this project
This project has 2 applications on record. Each is a separate step (an impact study, an approval, an expansion…):
| Filing | Status | Land | Cost |
|---|---|---|---|
| New project filed 22 Nov 2023 | Under forest review | 107.9 acres | ₹1,200 crore |
| New project filed 8 Nov 2023 (this page) | More information requested | 107.9 acres | ₹1,200 crore |
In context
13 applications in Palghar since January 2022 are in the same category (Railways & metro): 3 approved, 6 filed or under review, and 4 withdrawn, lapsed or rejected. At 107.9 acres, this one is larger than 50% of them.
4 other applications of any kind have been filed within 5 km of this site since January 2022.
Where it is
Asangaon, Dahanu, Palghar, Maharashtra. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.
Other projects nearby
- "New EMU Carshed cum POH Workshop" at Vangaon on Western Railway under MUTP-… — under forest review, 0 m away
- Railway Over Bridge in lieu of LC 55 at Km 143/00 on Western Railway Line on… — more information requested, 2.4 km away
- Railway Over Bridge in lieu of LC 55 at Km 143/00 on Western Railway Line on… — lapsed, 2.4 km away
- Widening and Strengthening of the existing road (ODR 35) from the village… — under forest review, 4.3 km away
- 8 lane Access controlled Highways For Connectivity to Proposed Vadhavan Port… — in-principle approval, conditions pending, 4.7 km away
- 8 Lane Access Controlled Highways For Connectivity to Proposed Vadhavan Port… — lapsed, 5.1 km away
- Request for Transfer of Environment Clearance (EC) (Change in the Name) from… — environmental approval granted, 5.6 km away
- Amendment in Environment Clearance of existing 500 MW (2 x 250 MW) Adani… — lapsed, 5.6 km away
More from Mumbai Railway Vikas Corporation Limited in Palghar
- Forest Clearance for Proposed Boisar Goods siding yard near Boisar station — forest land use approved
- Forest Clearance for Proposed Boisar Goods siding yard near Boisar station — lapsed
- Quadrupling of Virar Dahanu Road Railway Project under MUTP-III — application filed
5 Mumbai Railway Vikas Corporation projects in Palghar
All 6 Mumbai Railway Vikas Corporation projects across India
About this information
This page is compiled from publicly available approval records and rewritten in plain language. Statuses can change between our updates, so check with the authority before making decisions. Spotted a mistake? Tell us.