What is Approach Road to Private Land?
Approach Road to Private Land is a proposed road project in Kawir, Alibag, Raigarh, Maharashtra. The site covers 3.6 acres.
Who is building it?
The applicant is Umesh Shrimant Patil.
Has it been approved?
Not yet. The application is still under review: its status is “More information requested”, as of 27 Nov 2026.
Where is it?
In Kawir, Alibag, Raigarh, Maharashtra.
How big is it?
It has a stated cost of ₹55 lakh; a site of 3.6 acres and 1.7 acres (0.7 ha) of forest land.
When was it filed?
The application was filed on 2 Feb 2026.
Project details
| Status | More information requested |
|---|---|
| Status since | 7 Oct 2026 |
| Application filed | 2 Feb 2026 |
| Approval sought | Forest land use |
| Application type | New project |
| Sector | Roads & highways |
| Applicant | Umesh Shrimant Patil |
| Land area | 3.6 acres (1.4 ha) |
| Forest land | 1.7 acres (0.7 ha) |
| Project cost | ₹55 lakh |
| Village / locality | Kawir |
| Taluk / tehsil | Alibag |
| District | Raigarh |
| State | Maharashtra |
| Location from | Site boundary on record |
| Our reference | WID-MH-16236 |
In context
70 applications in Raigarh since January 2022 are in the same category (Roads & highways): 10 approved, 33 filed or under review, and 27 withdrawn, lapsed or rejected. The approved ones took a median of 22 months from filing to approval. At 3.6 acres, this one is smaller than 53% of them.
5 other applications of any kind have been filed within 5 km of this site since January 2022.
Where it is
Kawir, Alibag, Raigarh, Maharashtra. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.
Other projects nearby
- Approach Road to Private land — lapsed, 650 m away
- Diversion of Forest Land for Dismantling of the Existing Structurally Unsafe… — under forest review, 3 km away
- Diversion of Forest Land — in-principle approval, conditions pending, 3.2 km away
- Diversion of Forest Land for Dismantling of the Existing Structurally Unsafe… — under forest review, 3.4 km away
- Environment Clearance Design and Construction of 100 Seats Govt. Medical… — environmental approval granted, 4.6 km away
- CRZ clearance for proposed reconstruction of existing demolished house on GAT.… — returned to applicant, 5 km away
- 50 Ktpa Iso-Propyl Alcohol Unit at Gail Petrochemical Complex Usar — cleared for impact study, 5.1 km away
- CRZ Clearance for Proposed Eco Tourism-Vasahat & Beach Resort on GUT No.… — recommended by coastal authority, 5.1 km away
About this information
This page is compiled from publicly available approval records and rewritten in plain language. Statuses can change between our updates, so check with the authority before making decisions. Spotted a mistake? Tell us.