Environmental approval grantedIndustry · East Jaintia Hills, Meghalaya

Integrated Cement Plant with capacity of clinker: 0.95 million TPA, Cement: 0.99 million TPA (OPC, PPC, PSC, SRC, RHPC & Composite Cement) CPP: 15 MW, WHRS: 7 MW) and DG Sets 2500 KVA (1x2500 KVA or 2X1000 KVA & 1X500 KVA or 1x1000 KVA, 2x500 KVA & 2x250KVA) in Khara Siang Lum Pyrshin by Shree Cement Ltd

Integrated Cement Plant with capacity of clinker: 0.95 million TPA, Cement: 0.99 million TPA (OPC, PPC, PSC, SRC, RHPC & Composite Cement) CPP: 15 MW, WHRS: 7 MW) and DG Sets 2500 KVA (1x2500 KVA or 2X1000 KVA & 1X500 KVA or 1x1000 KVA, 2x500 KVA & 2x250KVA) in Khara Siang Lum Pyrshin by Shree Cement Ltd is an approved industrial project in Daistong, Saipung, East Jaintia Hills, Meghalaya. The site covers 150.9 acres. Its stated project cost is ₹1,264 crore. As of 27 Nov 2026, its status is “Environmental approval granted” (since 25 Apr 2026).

See it on the live map All projects in East Jaintia Hills

Data last refreshed 27 Nov 2026, 6:36 am IST. We check for new filings and status changes twice a day.

Quick answers

What is this project?

Integrated Cement Plant with capacity of clinker: 0.95 million TPA, Cement: 0.99 million TPA (OPC, PPC, PSC, SRC, RHPC & Composite Cement) CPP: 15 MW, WHRS: 7 MW) and DG Sets 2500 KVA (1x2500 KVA or 2X1000 KVA & 1X500 KVA or 1x1000 KVA, 2x500 KVA & 2x250KVA) in Khara Siang Lum Pyrshin by Shree Cement Ltd is an approved industrial project in Daistong, Saipung, East Jaintia Hills, Meghalaya. The site covers 150.9 acres.

Who is building it?

The applicant is Shree Cement Limited.

Has it been approved?

Yes. Its status is “Environmental approval granted” (since 25 Apr 2026), as of 27 Nov 2026.

Where is it?

In Daistong, Saipung, East Jaintia Hills, Meghalaya.

How big is it?

It has a stated cost of ₹1,264 crore and a site of 150.9 acres.

When was it filed?

The application was filed on 9 Apr 2026.

Project details

Official titleIntegrated Cement Plant with capacity of clinker: 0.95 million TPA, Cement: 0.99 million TPA (OPC, PPC, PSC, SRC, RHPC & Composite Cement) CPP: 15 MW, WHRS: 7 MW) and DG Sets 2500 KVA (1x2500 KVA or 2X1000 KVA & 1X500 KVA or 1x1000 KVA, 2x500 KVA & 2x250KVA) in Khara Siang Lum Pyrshin in Daistong village, Elaka: Nongkhlieh Dolloiship, District of East Jaintia Hills (Meghalaya) by Shree Cement Ltd.
StatusEnvironmental approval granted
Status since25 Apr 2026
Application filed9 Apr 2026
Approval soughtEnvironmental approval
Application typeAmendment
SectorIndustry
ApplicantShree Cement Limited
Land area150.9 acres (61.1 ha)
Project cost₹1,264 crore
Village / localityDaistong
Taluk / tehsilSaipung
DistrictEast Jaintia Hills
StateMeghalaya
Location fromSite boundary on record
Our referenceWID-ML-00287

All filings for this project

This project has 4 applications on record. Each is a separate step (an impact study, an approval, an expansion…):

FilingStatusLandCost
Amendment filed 9 Apr 2026 (this page)Environmental approval granted150.9 acres₹1,264 crore
New project filed 23 Feb 2026Environmental approval granted150.9 acres₹1,264 crore
New project filed 23 Feb 2026Withdrawn150.9 acres₹1,264 crore
Early planning filed 29 Sept 2025Cleared for impact study150.9 acres₹1,264 crore

In context

12 applications in East Jaintia Hills since January 2022 are in the same category (Industry): 6 approved, 3 filed or under review, and 3 withdrawn, lapsed or rejected. The approved ones took a median of 3 months from filing to approval. At 150.9 acres, this one is smaller than 92% of them.

4 other applications of any kind have been filed within 5 km of this site since January 2022.

Where it is

Daistong, Saipung, East Jaintia Hills, Meghalaya. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.

Other projects nearby

More from Shree Cement Limited in East Jaintia Hills

6 Shree Cement projects in East Jaintia Hills
All 63 Shree Cement projects across India

About this information

This page is compiled from publicly available approval records and rewritten in plain language. Statuses can change between our updates, so check with the authority before making decisions. Spotted a mistake? Tell us.