Quick answers
What is Chachai Aabad Sand Mine?
Chachai Aabad Sand Mine is an approved mining project in Chachai Abad, Anuppur, Madhya Pradesh. The site covers 12.4 acres.
Who is building it?
The applicant is Pramod Saxena.
Has it been approved?
Yes. Its status is “Environmental approval granted” (since 11 Jul 2023), as of 27 Nov 2026.
Where is it?
In Chachai Abad, Anuppur, Madhya Pradesh.
How big is it?
It has a stated cost of ₹1.1 crore and a site of 12.4 acres.
When was it filed?
The application was filed on 11 Jul 2023.
Project details
| Status | Environmental approval granted |
|---|---|
| Status since | 11 Jul 2023 |
| Application filed | 11 Jul 2023 |
| Approval sought | Environmental approval |
| Application type | New project |
| Sector | Mining |
| Applicant | Pramod Saxena |
| Land area | 12.4 acres (5 ha) |
| Project cost | ₹1.1 crore |
| Village / locality | Chachai Abad |
| Taluk / tehsil | Anuppur |
| District | Anuppur |
| State | Madhya Pradesh |
| Location from | Site boundary on record |
| Our reference | WID-MP-01232 |
In context
134 applications in Anuppur since January 2022 are in the same category (Mining): 45 approved, 29 filed or under review, and 60 withdrawn, lapsed or rejected. The approved ones took a median of 3 months from filing to approval. At 12.4 acres, this one is larger than 70% of them.
No other mining lease on record is within 500 m of this site; 1 has applied within 5 km.
Where it is
Chachai Abad, Anuppur, Madhya Pradesh. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.
Other projects nearby
- Ridiversion of 1.7827 Ha of Forest Land for Laying of Water Pipe Line and… — more information requested, 1.2 km away
- 5MW Solar Plant, Vivek Nagar Closed Underground Mine, SECL, Sohagpur Area. — more information requested, 2.9 km away
- 1x660 MW Amarkantak Ultra Supercritical Thermal Power Project — withdrawn, 3.2 km away
- 1x660 MW Amarkantak Ultra Supercritical Thermal Power Project — environmental approval granted, 3.2 km away
- 1x660 MW Amarkantak Ultra Supercritical Thermal Power Project — returned to applicant, 3.2 km away
- 1x210 MW Amarkantak Thermal Power Station — lapsed, 3.2 km away
- Manpur Sand Mine — not approved, 4 km away
- Manpur Sand Mine — cleared for impact study, 4 km away
More from Pramod Saxena in Anuppur
- Cholna Sand Mine — lapsed
- Khujarwar Sand Quarry — lapsed
- Manpur Sand Mine — not approved
- Pasan Sand Mine — lapsed
- Balbehra Sand Quarry — environmental approval granted
- Balbehra Umariya Sand Quarry — environmental approval granted
About this information
This page is compiled from publicly available approval records and rewritten in plain language. Statuses can change between our updates, so check with the authority before making decisions. Spotted a mistake? Tell us.