Quick answers
What is this project?
Shahpur Sand quarry Of M/s NATIONAL ENERGY TRADING AND SERVICES LIMITED is an approved mining project in Shahpur, Betul, Madhya Pradesh. The site covers 27.2 acres.
Who is building it?
The applicant is National Energy Trading and Services Limited.
Has it been approved?
Yes. Its status is “Environmental approval granted” (since 15 Apr 2023), as of 27 Nov 2026.
Where is it?
In Shahpur, Betul, Madhya Pradesh.
How big is it?
It has a stated cost of ₹40 lakh and a site of 27.2 acres.
When was it filed?
The application was filed on 15 Apr 2023.
Project details
| Status | Environmental approval granted |
|---|---|
| Status since | 15 Apr 2023 |
| Application filed | 15 Apr 2023 |
| Approval sought | Environmental approval |
| Application type | New project |
| Sector | Mining |
| Applicant | National Energy Trading and Services Limited |
| Land area | 27.2 acres (11 ha) |
| Project cost | ₹40 lakh |
| Village / locality | Shahpur |
| Taluk / tehsil | Shahpur |
| District | Betul |
| State | Madhya Pradesh |
| Location from | Site boundary on record |
| Our reference | WID-MP-02534 |
In context
166 applications in Betul since January 2022 are in the same category (Mining): 118 approved, 16 filed or under review, and 32 withdrawn, lapsed or rejected. The approved ones took a median of 43 days from filing to approval. At 27.2 acres, this one is larger than 89% of them.
1 other mining lease has applied within 500 m of this site; together with this one they cover 31.7 acres. Under India's environmental rules, mining leases less than 500 m apart are assessed together as one cluster, so the combined area can decide which clearance is needed. 3 mining leases have applied within 5 km.
Where it is
Shahpur, Betul, Madhya Pradesh. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.
Other projects nearby
- Mining Project of Patauvapura Sand Mine — environmental approval granted, 250 m away
- Pathai Sand Quarry (1.300 Ha) — lapsed, 1.2 km away
- Jampani Stone Quarry — environmental approval granted, 3.4 km away
- Bsnl 4g Saturation Project — lapsed, 4.2 km away
- Bsnl 4g Saturation Project — lapsed, 6.8 km away
- New 33/11 KV Substation — lapsed, 8.2 km away
- Construction of 33/11 KV Electric Substation at Village-Gurgunda — lapsed, 8.2 km away
- Diversion of Forest Land for Proposed of 3rd Railway Line Between Jujharpur… — more information requested, 9.2 km away
More from National Energy Trading and Services Limited in Betul
- 24.970ha Baspur/Shiv Sagar/Gonapur Auctioned Sand Quarry — environmental approval granted
- Guwadi Sand Mine — environmental approval granted
- Ratamati Sand Mine — environmental approval granted
- Loniya Sand Mine — environmental approval granted
All 5 National Energy Trading projects across India
About this information
This page is compiled from publicly available approval records and rewritten in plain language. Statuses can change between our updates, so check with the authority before making decisions. Spotted a mistake? Tell us.