Quick answers
What is Gudhapali Pyrophyllite and Diaspore Mine?
Gudhapali Pyrophyllite and Diaspore Mine is a lapsed mining project in Gura, Palera, Tikamgarh, Madhya Pradesh. The site covers 3.7 acres.
Who is building it?
The applicant is Sanjay Jain.
Has it been approved?
No. The application was lapsed on 19 Feb 2025, so it is no longer under consideration.
Where is it?
In Gura, Palera, Tikamgarh, Madhya Pradesh.
How big is it?
It has a stated cost of ₹30 lakh and a site of 3.7 acres.
When was it filed?
The application was filed on 2 Dec 2024.
Project details
| Status | Lapsed |
|---|---|
| Status since | 19 Feb 2025 |
| Application filed | 2 Dec 2024 |
| Approval sought | Environmental approval |
| Application type | New project |
| Sector | Mining |
| Applicant | Sanjay Jain |
| Land area | 3.7 acres (1.5 ha) |
| Project cost | ₹30 lakh |
| Village / locality | Gura |
| Taluk / tehsil | Palera |
| District | Tikamgarh |
| State | Madhya Pradesh |
| Location from | Site boundary on record |
| Our reference | WID-MP-03245 |
In context
116 applications in Tikamgarh since January 2022 are in the same category (Mining): 61 approved, 18 filed or under review, and 37 withdrawn, lapsed or rejected. The approved ones took a median of 4 months from filing to approval. At 3.7 acres, this one is smaller than 91% of them.
No other mining lease on record is within 500 m of this site; 2 have applied within 5 km.
Where it is
Gura, Palera, Tikamgarh, Madhya Pradesh. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.
Other projects nearby
- Gudapali Pyrophyllite & Diaspore mine — under environmental review, 2.2 km away
- Gudapali Pyrophyllite and Diaspore Mine — lapsed, 2.2 km away
- Tanga Sand Quarry — environmental approval granted, 6.1 km away
- 33 K.V electric power transmission line from village Khaira Tigaila (Albeli… — lapsed, 6.6 km away
- 33 K.V electric power transmission line from village Khaira Tigaila (Albeli… — forest land use approved, 7.3 km away
- Land Allotment for Muktidham Construction — more information requested, 9.1 km away
- Thar Stone (Gitti & M-sand) Quarry — lapsed, 10.2 km away
- Thar Stone Quarry — environmental approval granted, 10.2 km away
More from Sanjay Jain in Tikamgarh
- Gudapali Pyrophyllite & Diaspore mine — under environmental review
- Gudapali Pyrophyllite and Diaspore Mine — lapsed
About this information
This page is compiled from publicly available approval records and rewritten in plain language. Statuses can change between our updates, so check with the authority before making decisions. Spotted a mistake? Tell us.