One of 2 filings for this project. The project's main page, with every filing and where each stands: Proposed Expansion of existing synthetic organic chemicals unit, M/s Vini Industries at…
Project details
| Status | Cleared for impact study |
|---|---|
| Status since | 27 Jun 2024 |
| Application filed | 9 May 2024 |
| Approval sought | Environmental approval |
| Application type | Early planning |
| Sector | Industry |
| Applicant | Vini Industries |
| Land area | 1.1 acres (0.4 ha) |
| Project cost | ₹14.5 crore |
| Village / locality | Phatepura |
| Taluk / tehsil | Meghnagar |
| District | Jhabua |
| State | Madhya Pradesh |
| Location from | Site boundary on record |
| Our reference | WID-MP-04075 |
All filings for this project
This project has 2 applications on record. Each is a separate step (an impact study, an approval, an expansion…):
| Filing | Status | Land | Cost |
|---|---|---|---|
| Expansion filed 19 Jun 2025 | Environmental approval granted | 1.1 acres | ₹14.5 crore |
| Early planning filed 9 May 2024 (this page) | Cleared for impact study | 1.1 acres | ₹14.5 crore |
In context
14 applications in Jhabua since January 2022 are in the same category (Industry): 8 approved, 5 filed or under review, and 1 withdrawn, lapsed or rejected. The approved ones took a median of 2 months from filing to approval. At 1.1 acres, this one is smaller than 79% of them.
12 other applications of any kind have been filed within 5 km of this site since January 2022.
Where it is
Phatepura, Meghnagar, Jhabua, Madhya Pradesh. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.
Other projects nearby
- Proposed Expansion of existing synthetic organic chemicals unit, M/s Vini… — environmental approval granted, 0 m away
- Proposed production of DAP/NPK complex fertilizer from 3,30,000 TPA to… — initial checks, 350 m away
- Industrial project by M/s Devansh Trading Company — environmental approval granted, 450 m away
- Industrial project by M/s Devansh Trading Company — under environmental review, 450 m away
- Expansion of Ferro Alloy plant from 13,200 TPA (1 x 7 MVA SEAF) to 39,600 TPA… — cleared for impact study, 850 m away
- Ferro Alloy Plant (3 X 7 Mva) for Production of 13,200 Tpa of Ferro Manganese,… — environmental approval granted, 850 m away
- Proposed Project for Manufacturing of Active Pharmaceutical Ingredients and… — under environmental review, 1.1 km away
- Proposed Project for Manufacturing of Active Pharmaceutical Ingredients and… — cleared for impact study, 1.1 km away
About this information
This page is compiled from publicly available approval records and rewritten in plain language. Statuses can change between our updates, so check with the authority before making decisions. Spotted a mistake? Tell us.