One of 2 filings for this project. The project's main page, with every filing and where each stands: Badiya Limestone Block (Area- 3.625 ha.)
Project details
| Status | Cleared for impact study |
|---|---|
| Status since | 17 May 2025 |
| Application filed | 16 May 2025 |
| Approval sought | Environmental approval |
| Application type | Early planning |
| Sector | Mining |
| Applicant | Gourav Kushwaha |
| Land area | 9 acres (3.6 ha) |
| Project cost | ₹2 crore |
| Village / locality | Bariya |
| Taluk / tehsil | Gandhwani |
| District | Dhar |
| State | Madhya Pradesh |
| Location from | Site boundary on record |
| Our reference | WID-MP-07232 |
All filings for this project
This project has 2 applications on record. Each is a separate step (an impact study, an approval, an expansion…):
| Filing | Status | Land | Cost |
|---|---|---|---|
| New project filed 10 Nov 2025 | Environmental approval granted | 9 acres | ₹2 crore |
| Early planning filed 16 May 2025 (this page) | Cleared for impact study | 9 acres | ₹2 crore |
In context
364 applications in Dhar since January 2022 are in the same category (Mining): 203 approved, 35 filed or under review, and 126 withdrawn, lapsed or rejected. The approved ones took a median of 30 days from filing to approval. At 9 acres, this one is larger than 56% of them.
3 other mining leases have applied within 500 m of this site; together with this one they cover 41.2 acres. Under India's environmental rules, mining leases less than 500 m apart are assessed together as one cluster, so the combined area can decide which clearance is needed. 7 mining leases have applied within 5 km.
Where it is
Bariya, Gandhwani, Dhar, Madhya Pradesh. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.
Other projects nearby
- Badiya Limestone Block (Area- 3.625 ha.) — environmental approval granted, 0 m away
- Badiya Limestone Mine 4.999 Ha — lapsed, 150 m away
- Badiya Limestone Mine Area 4.028 Ha — lapsed, 450 m away
- 4.028 ha Badiya Limestone Mine — environmental approval granted, 450 m away
- Badiya Limestone Mine 4.50 ha — lapsed, 1.3 km away
- Transfer / Name Change in the Environment Clearance granted for "Limestone… — under environmental review, 2.1 km away
- Expansion of Cement Plant Capacity ; Clinker 0.825 MTPA to 1.10 MTPA, Cement:… — environmental approval granted, 3.1 km away
- Expansion of Cement Plant Capacity ; Clinker 0.825 MTPA to 1.10 MTPA, Cement:… — cleared for impact study, 3.1 km away