Quick answers
What is Bhuki (Gitti & M-sand) Quarry?
Bhuki (Gitti & M-sand) Quarry is a lapsed mining project in Bhuki, Mandsaur, Madhya Pradesh. The site covers 8.2 acres.
Who is building it?
The applicant is Vipin Kumar Sharma.
Has it been approved?
No. The application was lapsed on 16 Mar 2025, so it is no longer under consideration.
Where is it?
In Bhuki, Mandsaur, Madhya Pradesh.
How big is it?
It has a stated cost of ₹35 lakh and a site of 8.2 acres.
When was it filed?
The application was filed on 23 Jan 2025.
Project details
| Status | Lapsed |
|---|---|
| Status since | 16 Mar 2025 |
| Application filed | 23 Jan 2025 |
| Approval sought | Environmental approval |
| Application type | New project |
| Sector | Mining |
| Applicant | Vipin Kumar Sharma |
| Land area | 8.2 acres (3.3 ha) |
| Project cost | ₹35 lakh |
| Village / locality | Bhuki |
| Taluk / tehsil | Mandsaur |
| District | Mandsaur |
| State | Madhya Pradesh |
| Location from | Site boundary on record |
| Our reference | WID-MP-07486 |
In context
252 applications in Mandsaur since January 2022 are in the same category (Mining): 130 approved, 38 filed or under review, and 84 withdrawn, lapsed or rejected. The approved ones took a median of 4 months from filing to approval. At 8.2 acres, this one is larger than 77% of them.
No other mining lease on record is within 500 m of this site; 23 have applied within 5 km.
Where it is
Bhuki, Mandsaur, Madhya Pradesh. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.
Other projects nearby
- Capacity Expansion of Existing Fertilizer Unit — environmental approval granted, 1.8 km away
- Capacity Expansion of Existing Fertilizer Unit — cleared for impact study, 1.8 km away
- Sukri Crusher Stone Quarry — lapsed, 2.1 km away
- Dodiyameena Stone (Gitti) Quarry Project — environmental approval granted, 2.2 km away
- Dodiyameena Stone (Gitti) Quarry, — lapsed, 2.2 km away
- Dodiyameena Stone (Gitti) Quarry Project — cleared for impact study, 2.2 km away
- Palewan Stone Quarry; Quarry Lease Area- 1.00 ha, Production Capacity - 8,120… — cleared for impact study, 2.2 km away
- Proposed Dodiyamina Stone and M-Sand Quarry of Mr. Rohit Kumar — initial checks, 2.2 km away
About this information
This page is compiled from publicly available approval records and rewritten in plain language. Statuses can change between our updates, so check with the authority before making decisions. Spotted a mistake? Tell us.