Quick answers
What is Electrification Work in Neelkanth Ashram at Village Miriya?
Electrification Work in Neelkanth Ashram at Village Miriya is a lapsed power project in R.F, Pushparajgarh, Anuppur, Madhya Pradesh. The site covers 2.5 acres.
Who is building it?
The applicant is Rural Development.
Has it been approved?
No. The application was lapsed on 29 Oct 2024, so it is no longer under consideration.
Where is it?
In R.F, Pushparajgarh, Anuppur, Madhya Pradesh.
How big is it?
It has a stated cost of ₹6 lakh; a site of 2.5 acres and 1.5 acres (0.6 ha) of forest land.
When was it filed?
The application was filed on 18 Oct 2024.
Project details
| Status | Lapsed |
|---|---|
| Status since | 29 Oct 2024 |
| Application filed | 18 Oct 2024 |
| Approval sought | Forest land use |
| Application type | New project |
| Sector | Power |
| Applicant | Rural Development |
| Land area | 2.5 acres (1 ha) |
| Forest land | 1.5 acres (0.6 ha) |
| Project cost | ₹6 lakh |
| Village / locality | R.F |
| Taluk / tehsil | Pushparajgarh |
| District | Anuppur |
| State | Madhya Pradesh |
| Location from | Site boundary on record |
| Our reference | WID-MP-09569 |
In context
34 applications in Anuppur since January 2022 are in the same category (Power): 13 approved, 7 filed or under review, and 14 withdrawn, lapsed or rejected. The approved ones took a median of 2 months from filing to approval. At 2.5 acres, this one is smaller than 88% of them.
2 other applications of any kind have been filed within 5 km of this site since January 2022.
Where it is
R.F, Pushparajgarh, Anuppur, Madhya Pradesh. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.
Other projects nearby
- Harrai PMGSY (Chhatta tola) to Miriya — more information requested, 1.5 km away
- Harrai PMGSY (Chhatta tola) to Miriya — more information requested, 1.5 km away
- Electrification Work at Village Barsot(Damgarh) Under Pvtg Scheme — lapsed, 5.1 km away
- Chachandih Bauxite Mine (148.181 hect) — forest land use approved, 8.5 km away
- Bharti Airtel Ltd. 5G OFC Project Amarkantak-Sarai-Shahdol Route DFO ANUPPUR — forest land use approved, 8.8 km away
- Electrification Work at Village Kekariya Tanajatola Under Pvtg Scheme — lapsed, 9.2 km away
- Electrification Work at Village Boda Under Pvtg Scheme — lapsed, 9.9 km away
- PWD road to Sarhakona — lapsed, 10.2 km away
More from Rural Development in Anuppur
- Bifurcation of 33 KV Kotma old feeder from 132 KV EHV S/S to 33/11 KV S/S… — lapsed
- Work of 33 KV Line for New 33/11 KV Substation — forest land use approved
- Bifurcation of 33 KV Feeder from 132 KV EHV S/S to 33/11 KV S/S Funga — forest land use approved
- Electrification work of PVTG Habitation Village Akua, Census code-501932 — lapsed
- Stringing of additional 33 KV Line from 33/11 KV S/S Funga to Pasla Village — forest land use approved
- Bifurcation of 33 KV Feeder from 33/11 KV S/S Parasi to 33/11 KV S/S Jaithari — lapsed
About this information
This page is compiled from publicly available approval records and rewritten in plain language. Statuses can change between our updates, so check with the authority before making decisions. Spotted a mistake? Tell us.