Quick answers
What is this project?
Forest Clearance in Baghannara Gram Panchayat Chandpur Block Pali for Electrification of Pvtg (Baiga) Communities is a lapsed power project in Chandpur, Pali, Umaria, Madhya Pradesh. The site covers 5.4 acres.
Who is building it?
The applicant is Ankit Raj.
Has it been approved?
No. The application was lapsed on 19 Nov 2025, so it is no longer under consideration.
Where is it?
In Chandpur, Pali, Umaria, Madhya Pradesh.
How big is it?
It has a stated cost of ₹56 lakh; a site of 5.4 acres and 2.3 acres (1 ha) of forest land.
When was it filed?
The application was filed on 24 Oct 2024.
Project details
| Official title | Proposal for Forest Clearance in Baghannara Gram Panchayat Chandpur Block Pali for Electrification of Pvtg (Baiga) Communities |
|---|---|
| Status | Lapsed |
| Status since | 19 Nov 2025 |
| Application filed | 24 Oct 2024 |
| Approval sought | Forest land use |
| Application type | New project |
| Sector | Power |
| Applicant | Ankit Raj |
| Land area | 5.4 acres (2.2 ha) |
| Forest land | 2.3 acres (1 ha) |
| Project cost | ₹56 lakh |
| Village / locality | Chandpur |
| Taluk / tehsil | Pali |
| District | Umaria |
| State | Madhya Pradesh |
| Location from | Site boundary on record |
| Our reference | WID-MP-10021 |
In context
17 applications in Umaria since January 2022 are in the same category (Power): 0 approved, 7 filed or under review, and 10 withdrawn, lapsed or rejected. At 5.4 acres, this one is smaller than 94% of them.
9 other applications of any kind have been filed within 5 km of this site since January 2022.
Where it is
Chandpur, Pali, Umaria, Madhya Pradesh. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.
Other projects nearby
- Jio Digital Fiber Pvt Ltd Linear Ofc 5g Project In Row Corridor Of Principal… — forest land use approved, 1.4 km away
- Jio Digital Fiber Pvt Ltd Linear Ofc 5g Project In Row Corridor Of Principal… — forest land use approved, 2.6 km away
- Marwatola VII Coal Mine (Area: 1200 Ha) with Coal Production Capacity by… — environmental approval granted, 3.6 km away
- Marwatola VII Coal Mine (Area: 1200 Ha) with Coal Production Capacity by… — cleared for impact study, 3.6 km away
- Marwatola VII Coal Mine (Area: 1200 Ha) with Coal Production Capacity by… — cleared for impact study, 3.6 km away
- Marwatola VII Coal Mine (Area: 1200 Ha) with Coal Production Capacity by… — cleared for impact study, 3.6 km away
- Marwatola-Vii Coal Mine — in-principle approval, conditions pending, 3.6 km away
- Road Construction Under PMGSY-4 ,Road Name-Shahpur Audhera Amgar Road to Dadra… — more information requested, 3.9 km away
About this information
This page is compiled from publicly available approval records and rewritten in plain language. Statuses can change between our updates, so check with the authority before making decisions. Spotted a mistake? Tell us.