Quick answers
What is Khategaon Kannod Multi village Drinking water supply schemes?
Khategaon Kannod Multi village Drinking water supply schemes is an approved water and irrigation project in Godwai, Kannod, Dewas, Madhya Pradesh. The site covers 17 acres.
Who is building it?
The applicant is Madhya Pradesh Jal Nigam Maryadit.
Has it been approved?
Yes. Its status is “Forest land use approved” (since 13 Aug 2026), as of 27 Nov 2026.
Where is it?
In Godwai, Kannod, Dewas, Madhya Pradesh.
How big is it?
It has a stated cost of ₹471.5 crore; a site of 17 acres and 16.9 acres (6.8 ha) of forest land.
When was it filed?
The application was filed on 24 Jul 2025.
Project details
| Status | Forest land use approved |
|---|---|
| Status since | 13 Aug 2026 |
| Application filed | 24 Jul 2025 |
| Approval sought | Forest land use |
| Application type | New project |
| Sector | Water & irrigation |
| Applicant | Madhya Pradesh Jal Nigam Maryadit |
| Land area | 17 acres (6.9 ha) |
| Forest land | 16.9 acres (6.8 ha) |
| Project cost | ₹471.5 crore |
| Village / locality | Godwai |
| Taluk / tehsil | Kannod |
| District | Dewas |
| State | Madhya Pradesh |
| Location from | Site boundary on record |
| Our reference | WID-MP-10187 |
In context
18 applications in Dewas since January 2022 are in the same category (Water & irrigation): 10 approved, 5 filed or under review, and 2 withdrawn, lapsed or rejected. The approved ones took a median of 6 months from filing to approval. At 17 acres, this one is smaller than 59% of them.
1 other applications of any kind have been filed within 5 km of this site since January 2022.
Where it is
Godwai, Kannod, Dewas, Madhya Pradesh. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.
Other projects nearby
- Ambada Stone Quarry — lapsed, 4.7 km away
- Bagankheda To Thuriya Road — lapsed, 8.3 km away
- Maa Rewa Lift Irrigation Project — lapsed, 10.7 km away
- 220 KV DCDS Ashta Kannod Transmission Line — lapsed, 11 km away
- Bharti Airtel Limited Linear OFC 5G Project in RoW Chapda-Punjapura-Khategaon… — forest land use approved, 11.5 km away
- Badhawa Stone Quarry — environmental approval granted, 12 km away
- 132 KV Transmission Line to Ph3 of Narmada Parwati Phase-I & II Micro Lift… — lapsed, 13 km away
- Nanasa Stone, M-Sand & Murrum Mine — cleared for impact study, 13.1 km away
More from Madhya Pradesh Jal Nigam Maryadit in Dewas
- Khategaon-Kannod Multi Village Drinking Water Scheme — forest land use approved
- Khategaon-Kannod MVS water supply scheme District Dewas — decision issued
3 Madhya Pradesh Jal Nigam Maryadit projects in Dewas
All 51 Madhya Pradesh Jal Nigam Maryadit projects across India
About this information
This page is compiled from publicly available approval records and rewritten in plain language. Statuses can change between our updates, so check with the authority before making decisions. Spotted a mistake? Tell us.