Project details
| Status | More information requested |
|---|---|
| Status since | 23 Sept 2026 |
| Application filed | 1 Dec 2025 |
| Approval sought | Forest land use |
| Application type | New project |
| Sector | Power |
| Applicant | Sandeep Dhurve |
| Land area | 693.7 acres (280.8 ha) |
| Forest land | 65.8 acres (26.6 ha) |
| Project cost | ₹3.3 crore |
| Village / locality | Harduli |
| Taluk / tehsil | Kurai |
| District | Seoni |
| State | Madhya Pradesh |
| Location from | Site boundary on record |
| Our reference | WID-MP-10445 |
In context
15 applications in Seoni since January 2022 are in the same category (Power): 6 approved, 5 filed or under review, and 4 withdrawn, lapsed or rejected. The approved ones took a median of 15 months from filing to approval. At 693.7 acres, this one is larger than 73% of them.
Where it is
Harduli, Kurai, Seoni, Madhya Pradesh. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.
Other projects nearby
- Project for Laying of 33KV Line Village Mohgao to Khawasa Under Seoni — lapsed, 0 m away
- Jio Digital Fiber Pvt Ltd Linear OFC 5G Project in ROW Corridor of Principal… — more information requested, 7.3 km away
- Jio Digital Fiber Pvt Ltd Linear OFC 5G Project in ROW Corridor of Principal… — under wildlife review, 7.3 km away
- Jio Digital Fiber Pvt Ltd Linear OFC 5G Project in ROW Corridor of Principal… — lapsed, 7.3 km away
- Khairghat River Sand Quarry — environmental approval granted, 8.6 km away
- Jio Digital Fiber Pvt Ltd Linear OFC 5G Project in ROW Corridor of Principal… — more information requested, 11.5 km away
- 33KV Feeder From Riddi to Pindrai — in-principle approval, conditions pending, 12 km away
- Bsnl 4g Saturation — under wildlife review, 12.9 km away
More from Sandeep Dhurve in Seoni
- Bifurcation of 33kV ARI feeder — more information requested
- 33KV Feeder From Riddi to Pindrai — in-principle approval, conditions pending
- Bifurcation of 33kV ARI feeder — lapsed
- Project for Erection of 33/11KV Substation — lapsed
- Project for Laying of 33KV Line Village Mohgao to Khawasa Under Seoni — lapsed
About this information
This page is compiled from publicly available approval records and rewritten in plain language. Statuses can change between our updates, so check with the authority before making decisions. Spotted a mistake? Tell us.