What is 132 KV Kapasi - Gadla Transmission Line?
132 KV Kapasi - Gadla Transmission Line is a lapsed power project in Kalora, Bamori, Guna, Madhya Pradesh. The site covers 11.4 acres.
Who is building it?
The applicant is Mpptcl.
Has it been approved?
No. The application was lapsed on 23 Oct 2024, so it is no longer under consideration.
Where is it?
In Kalora, Bamori, Guna, Madhya Pradesh.
How big is it?
It has a stated cost of ₹30 crore; a site of 11.4 acres and 11.4 acres (4.6 ha) of forest land.
When was it filed?
The application was filed on 27 Apr 2023.
Project details
| Status | Lapsed |
|---|---|
| Status since | 23 Oct 2024 |
| Application filed | 27 Apr 2023 |
| Approval sought | Forest land use |
| Application type | New project |
| Sector | Power |
| Applicant | Mpptcl |
| Land area | 11.4 acres (4.6 ha) |
| Forest land | 11.4 acres (4.6 ha) |
| Project cost | ₹30 crore |
| Village / locality | Kalora |
| Taluk / tehsil | Bamori |
| District | Guna |
| State | Madhya Pradesh |
| Location from | Site boundary on record |
| Our reference | WID-MP-10686 |
In context
35 applications in Guna since January 2022 are in the same category (Power): 13 approved, 5 filed or under review, and 17 withdrawn, lapsed or rejected. The approved ones took a median of 13 months from filing to approval. At 11.4 acres, this one is smaller than 76% of them.
4 other applications of any kind have been filed within 5 km of this site since January 2022.
Where it is
Kalora, Bamori, Guna, Madhya Pradesh. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.
Other projects nearby
- Panheti Medium Irrigation Project — lapsed, 2.3 km away
- Panheti Irrigation Project — more information requested, 2.4 km away
- Jio Digital Fiber Pvt. Ltd. Linear Ofc 5g Project In Row Corridor Of Principal… — forest land use approved, 3.4 km away
- Telecom project by Bharti Airtel Ltd. — forest land use approved, 4 km away
- Guna – Fatehgarh – Paron Road — forest land use approved, 8.7 km away
- Gopi Krishna Mvs — forest land use approved, 8.9 km away
- Jio Digital Fiber Pvt Ltd Linear OFC 5G Project in ROW Corridor of Principal… — lapsed, 9.4 km away
- Jio Digital Fiber Pvt Ltd Linear OFC 5G Project in ROW Corridor of Principal… — forest land use approved, 10.5 km away
More from Mpptcl in Guna
- 132 KV Guna - Gadla DCDS Transmission line — forest land use approved
- 132 KV DCSS Gadla - Myana line — lapsed
About this information