Quick answers
What is 132 KV Guna - Gadla DCDS Transmission line?
132 KV Guna - Gadla DCDS Transmission line is an approved power project in Goria, Bamori, Guna, Madhya Pradesh. The site covers 1,571.5 acres.
Who is building it?
The applicant is Mpptcl.
Has it been approved?
Yes. Its status is “Forest land use approved” (since 19 Nov 2026), as of 27 Nov 2026.
Where is it?
In Goria, Bamori, Guna, Madhya Pradesh.
How big is it?
It has a stated cost of ₹60.6 crore; a site of 1,571.5 acres and 34.9 acres (14.1 ha) of forest land.
When was it filed?
The application was filed on 28 Jun 2025.
Project details
| Status | Forest land use approved |
|---|---|
| Status since | 19 Nov 2026 |
| Application filed | 28 Jun 2025 |
| Approval sought | Forest land use |
| Application type | New project |
| Sector | Power |
| Applicant | Mpptcl |
| Land area | 1,571.5 acres (636 ha) |
| Forest land | 34.9 acres (14.1 ha) |
| Project cost | ₹60.6 crore |
| Village / locality | Goria |
| Taluk / tehsil | Bamori |
| District | Guna |
| State | Madhya Pradesh |
| Location from | Site boundary on record |
| Our reference | WID-MP-11718 |
In context
35 applications in Guna since January 2022 are in the same category (Power): 13 approved, 5 filed or under review, and 17 withdrawn, lapsed or rejected. The approved ones took a median of 13 months from filing to approval. At 1,571.5 acres, this one is larger than 91% of them.
Where it is
Goria, Bamori, Guna, Madhya Pradesh. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.
Other projects nearby
- Gopi Krishna Sagar Mvs Guna — forest land use approved, 6.3 km away
- Gopi Krishna Mvrwss — forest land use approved, 7.2 km away
- Diversion of 0.0232 Ha of Forest Land for Construction of Mobile Tower at… — lapsed, 8.2 km away
- Gopi Krishna Mvs — forest land use approved, 8.8 km away
- Diversion of Forest Land for Construction of Mobile Tower — forest land use approved, 8.8 km away
- Jio Digital Fiber Pvt Ltd Linear OFC 5G Project in ROW Corridor of Principal… — forest land use approved, 9.6 km away
- Jio Digital Fiber Pvt Ltd Linear OFC 5G Project in ROW Corridor of Principal… — lapsed, 10 km away
- Telecom project by Bharti Airtel Ltd. — forest land use approved, 10.6 km away
More from Mpptcl in Guna
- 132 KV DCSS Gadla - Myana line — lapsed
- 132 KV Kapasi - Gadla Transmission Line — lapsed
About this information
This page is compiled from publicly available approval records and rewritten in plain language. Statuses can change between our updates, so check with the authority before making decisions. Spotted a mistake? Tell us.