Quick answers
What is this project?
Expansion of Integrated Steel Plant(Installation of 1x500 TPD DRI Plant alongwith 30 MW Captive Power Plant(15 MW- AFBC; 15 MW - WHRB) is a withdrawn industrial project in Upara R>Iguda, Kendujhar Sadar, Kendujhar, Odisha. The site covers 149.8 acres.
Who is building it?
The applicant is Sree Metaliks Limited.
Has it been approved?
No. The application was withdrawn on 7 Aug 2023, so it is no longer under consideration.
Where is it?
In Upara R>Iguda, Kendujhar Sadar, Kendujhar, Odisha.
How big is it?
It has a stated cost of ₹438.8 crore and a site of 149.8 acres.
When was it filed?
The application was filed on 28 Jul 2023.
Project details
| Official title | Expansion of Integrated Steel Plant(Installation of 1x500 TPD DRI Plant alongwith 30 MW Captive Power Plant(15 MW- AFBC; 15 MW - WHRB) located at Village- Anra, Tehsil- Telkoi, Dist- Keonjhar, Odisha. |
|---|---|
| Status | Withdrawn |
| Status since | 7 Aug 2023 |
| Application filed | 28 Jul 2023 |
| Approval sought | Environmental approval |
| Application type | Early planning |
| Sector | Industry |
| Applicant | Sree Metaliks Limited |
| Land area | 149.8 acres (60.6 ha) |
| Project cost | ₹438.8 crore |
| Village / locality | Upara R>Iguda |
| Taluk / tehsil | Kendujhar Sadar |
| District | Kendujhar |
| State | Odisha |
| Location from | Site boundary on record |
| Our reference | WID-OR-00159 |
In context
38 applications in Kendujhar since January 2022 are in the same category (Industry): 9 approved, 12 filed or under review, and 17 withdrawn, lapsed or rejected. The approved ones took a median of 2 months from filing to approval. At 149.8 acres, this one is larger than 61% of them.
6 other applications of any kind have been filed within 5 km of this site since January 2022.
Where it is
Upara R>Iguda, Kendujhar Sadar, Kendujhar, Odisha. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.
Other projects nearby
- Expansion of Integrated Steel Plant — withdrawn, 0 m away
- Change in Product Mix by means of installing 1X500 TPD DRI Plant — lapsed, 50 m away
- Expansion of Integrated Steel Plant (Installation of 1x500 TPD DRI Plant — returned to applicant, 50 m away
- Expansion of Integrated Steel Plant (Installation of 1x500 TPD DRI Plant — returned to applicant, 50 m away
- Expansion of Integrated Steel Plant (Installation of 1x500 TPD DRI Plant — initial checks, 50 m away
- Diversion of 9.1542 ha Forest Land out of total allotted area 133.6833 ha as… — under forest review, 300 m away
- Greenfield Project of Capacity 20,00,000 TPA (throughput) Iron Ore… — environmental approval granted, 5.5 km away
- Greenfield Project of Capacity 20,00,000 TPA (throughput) Iron Ore… — returned to applicant, 6 km away
More from Sree Metaliks Limited in Kendujhar
- Change in Product Mix by means of installing 1X500 TPD DRI Plant — lapsed
- Forest Clearance for Integrated Steel Plant of M/s Sree Metaliks Limited — more information requested
- Diversion of 9.1542 ha Forest Land out of total allotted area 133.6833 ha as… — under forest review
- Expansion of Integrated Steel Plant (Installation of 1x500 TPD DRI Plant — returned to applicant
- Expansion of Integrated Steel Plant (Installation of 1x500 TPD DRI Plant — returned to applicant
- Expansion of existing rolling mill (TMT Bars, Rolled product, wire Rods etc.)… — cleared for impact study
All 12 Sree Metaliks projects across India
About this information
This page is compiled from publicly available approval records and rewritten in plain language. Statuses can change between our updates, so check with the authority before making decisions. Spotted a mistake? Tell us.