Project details
| Status | Environmental approval granted |
|---|---|
| Status since | 6 May 2026 |
| Application filed | 18 May 2023 |
| Approval sought | Environmental approval |
| Application type | Amendment |
| Sector | Industry |
| Applicant | Bhushan Power & Steel Limited |
| Land area | 1,950.3 acres (789.3 ha) |
| Project cost | ₹24,600 crore |
| Village / locality | Kharhiapali |
| Taluk / tehsil | Thelkoloi |
| District | Sambalpur |
| State | Odisha |
| Location from | Site boundary on record |
| Our reference | WID-OR-00223 |
In context
38 applications in Sambalpur since January 2022 are in the same category (Industry): 17 approved, 13 filed or under review, and 8 withdrawn, lapsed or rejected. The approved ones took a median of 4 months from filing to approval. At 1,950.3 acres, this one is larger than 74% of them.
17 other applications of any kind have been filed within 5 km of this site since January 2022.
Where it is
Kharhiapali, Thelkoloi, Sambalpur, Odisha. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.
Other projects nearby
- Application for Split of Environmental Clearances (EC) issued to M/s. Bhushan… — more information requested, 200 m away
- Amendment in EC Conditions and Consolidation of all ECs issued to M/s. Bhushan… — more information requested, 200 m away
- Expansion of Crude Steel Production of Integrated Steel Plant from 4.50 MTPA… — not approved, 350 m away
- Expansion of Crude Steel Production of Integrated Steel Plant from 4.50 MTPA… — not approved, 350 m away
- Expansion of Crude Steel Production of Integrated Steel Plant From 4.50 MTPA… — cleared for impact study, 400 m away
- Expansion of Crude Steel Production of Integrated Steel Plant from 4.50 MTPA… — withdrawn, 1.8 km away
- Ash Dyke of Thermal Power Plant of NLC India Ltd. at Thelkolloi under Rengali… — forest land use approved, 2.1 km away
- Transfer of Environmental Clearance from Epsilon Carbon Ashoka Private Limited… — returned to applicant, 2.2 km away
More from Bhushan Power & Steel Limited in Sambalpur
- Application for Split of Environmental Clearances (EC) issued to M/s. Bhushan… — more information requested
- Amendment in EC Conditions and Consolidation of all ECs issued to M/s. Bhushan… — more information requested
- Expansion of Crude Steel Production of Integrated Steel Plant From 4.50 MTPA… — cleared for impact study
- Expansion of Crude Steel Production of Integrated Steel Plant from 4.50 MTPA… — not approved
- Expansion of Crude Steel Production of Integrated Steel Plant from 4.50 MTPA… — not approved
- Expansion of Crude Steel Production of Integrated Steel Plant from 4.50 MTPA… — withdrawn
7 Bhushan Power & Steel projects in Sambalpur
All 8 Bhushan Power & Steel projects across India
About this information
This page is compiled from publicly available approval records and rewritten in plain language. Statuses can change between our updates, so check with the authority before making decisions. Spotted a mistake? Tell us.