| Official title | Expansion by addition of 1x350 MW Imported Coal based Thermal Power Plant (Phase-ll) at village Kamalanga, in Odapada Taluk, Dhenkanal District, Odisha |
|---|---|
| Status | Withdrawn |
| Status since | 5 Sept 2024 |
| Application filed | 13 Oct 2023 |
| Approval sought | Environmental approval |
| Application type | Early planning |
| Sector | Power |
| Applicant | Gmr Kamalanga Energy Limited |
| Land area | 1,158.4 acres (468.8 ha) |
| Project cost | ₹7,493 crore |
| Village / locality | Senapatiberana |
| Taluk / tehsil | Motunga |
| District | Dhenkanal |
| State | Odisha |
| Location from | Site boundary on record |
| Our reference | WID-OR-00401 |
In context
8 applications in Dhenkanal since January 2022 are in the same category (Power): 3 approved, 2 filed or under review, and 3 withdrawn, lapsed or rejected.
16 other applications of any kind have been filed within 5 km of this site since January 2022.
Where it is
Senapatiberana, Motunga, Dhenkanal, Odisha. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.
Other projects nearby
- Expansion by addition of 1x350 MW Imported Coal based Thermal Power Plant… — under environmental review, 250 m away
- Expansion by addition of 1x350 MW Imported Coal based Thermal Power Plant… — environmental approval granted, 250 m away
- Expansion by addition of 1x350 MW Imported Coal based Thermal Power Plant… — environmental approval granted, 250 m away
- Expansion by addition of 1x350 MW Imported Coal based Thermal Power Plant… — cleared for impact study, 250 m away
- Re-Diversion of 9.628 Ha Forest Land in Dhenkanal Forest Division, Dhenkanal,… — not approved, 1.4 km away
- Submission of Replenishment Study Report of Environmental Clearance for… — not approved, 2.7 km away
- Damol Sand Quarry — environmental approval granted, 2.7 km away
- Damol Sand Quarry — lapsed, 2.7 km away
More from Gmr Kamalanga Energy Limited in Dhenkanal
- Expansion by addition of 1x350 MW Imported Coal based Thermal Power Plant… — under environmental review
- Re-Diversion of 9.628 Ha Forest Land in Dhenkanal Forest Division, Dhenkanal,… — not approved
- Expansion by addition of 1x350 MW Imported Coal based Thermal Power Plant… — environmental approval granted
- Expansion by addition of 1x350 MW Imported Coal based Thermal Power Plant… — environmental approval granted
- Expansion by addition of 1x350 MW Imported Coal based Thermal Power Plant… — cleared for impact study
All 6 Gmr Kamalanga Energy projects across India
About this information
This page is compiled from publicly available approval records and rewritten in plain language. Statuses can change between our updates, so check with the authority before making decisions. Spotted a mistake? Tell us.