Quick answers
What is Derenga Sand Quarry?
Derenga Sand Quarry is an approved mining project in Deranga, Kaniha, Anugul, Odisha. The site covers 15 acres.
Who is building it?
The applicant is Kishor Sahoo.
Has it been approved?
Yes. Its status is “Environmental approval granted” (since 30 Jan 2025), as of 27 Nov 2026.
Where is it?
In Deranga, Kaniha, Anugul, Odisha.
How big is it?
It has a stated cost of ₹1.2 crore and a site of 15 acres.
When was it filed?
The application was filed on 10 Dec 2024.
Project details
| Status | Environmental approval granted |
|---|---|
| Status since | 30 Jan 2025 |
| Application filed | 10 Dec 2024 |
| Approval sought | Environmental approval |
| Application type | New project |
| Sector | Mining |
| Applicant | Kishor Sahoo |
| Land area | 15 acres (6.1 ha) |
| Project cost | ₹1.2 crore |
| Village / locality | Deranga |
| Taluk / tehsil | Kaniha |
| District | Anugul |
| State | Odisha |
| Location from | Site boundary on record |
| Our reference | WID-OR-01308 |
In context
108 applications in Anugul since January 2022 are in the same category (Mining): 50 approved, 25 filed or under review, and 33 withdrawn, lapsed or rejected. The approved ones took a median of 3 months from filing to approval. At 15 acres, this one is smaller than 75% of them.
1 other mining lease has applied within 500 m of this site; together with this one they cover 45 acres. Under India's environmental rules, mining leases less than 500 m apart are assessed together as one cluster, so the combined area can decide which clearance is needed. 2 mining leases have applied within 5 km.
Where it is
Deranga, Kaniha, Anugul, Odisha. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.
Other projects nearby
- Derenga & Khajuria Sand Quarries Cluster Over an Area of 30.0 Acres Or 12.14… — lapsed, 0 m away
- Takua Sand Quarry over 8.30 ha onTikira River — cleared for impact study, 2.3 km away
- Takua Sand Quarry over 8.30 ha onTikira River — under environmental review, 2.3 km away
- Proposed Expansion of 1200 MW to 2000 MW by Installing 1x800 MW plant unit — returned to applicant, 3.9 km away
- Name Change in Environment Clearance (EC) Letter due to Change in Name of the… — environmental approval granted, 4 km away
- Expansion of Existing 1200MW by adding 3rd and 4th Unit of 660 MW ULTRA… — lapsed, 4.7 km away
- Modification of Ec on the Basis of Replenishment Study Report of Kampasala… — environmental approval granted, 6.3 km away
- Modification of Ec on the Basis of Replenishment Study Report of Kampasala… — not approved, 6.3 km away
About this information