Quick answers
What is this project?
Integrated Steel Plant[sponge Iron Plant(2,70,000tpa), Steel Billet ( 2,68,300 Tpa , Pig Iron (1,10,000 Tpa) is a lapsed industrial project in Uchab>Li, Bamebari, Kendujhar, Odisha. The site covers 87 acres.
Who is building it?
The applicant is Mgm Minerals Limited.
Has it been approved?
No. The application was lapsed on 16 Feb 2026, so it is no longer under consideration.
Where is it?
In Uchab>Li, Bamebari, Kendujhar, Odisha.
How big is it?
It has a stated cost of ₹237 crore and a site of 87 acres.
When was it filed?
The application was filed on 10 Aug 2024.
Project details
| Official title | Integrated Steel Plant[sponge Iron Plant(2,70,000tpa), Steel Billet ( 2,68,300 Tpa , Pig Iron (1,10,000 Tpa) Along With Captive Power Plant (35 MW ; 20 MW Whrb & 15 MW Afbc)] |
|---|---|
| Status | Lapsed |
| Status since | 16 Feb 2026 |
| Application filed | 10 Aug 2024 |
| Approval sought | Environmental approval |
| Application type | Ownership transfer |
| Sector | Industry |
| Applicant | Mgm Minerals Limited |
| Land area | 87 acres (35.2 ha) |
| Project cost | ₹237 crore |
| Village / locality | Uchab>Li |
| Taluk / tehsil | Bamebari |
| District | Kendujhar |
| State | Odisha |
| Location from | Site boundary on record |
| Our reference | WID-OR-01401 |
In context
38 applications in Kendujhar since January 2022 are in the same category (Industry): 9 approved, 12 filed or under review, and 17 withdrawn, lapsed or rejected. The approved ones took a median of 2 months from filing to approval. At 87 acres, this one is smaller than 61% of them.
19 other applications of any kind have been filed within 5 km of this site since January 2022.
Where it is
Uchab>Li, Bamebari, Kendujhar, Odisha. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.
Other projects nearby
- MGM MINERALS LIMITED (Steel Division-II) — lapsed, 0 m away
- Diversion of 0.469 Ha of Non-Forest Land Recorded As Forest As on 25.10.1980… — lapsed, 2.3 km away
- BHJ/BHQ Beneficiation Plant of 4 MTPA Throughput Capacity in Unchabali Iron… — lapsed, 2.9 km away
- BHJ/BHQ Beneficiation Plant of 4 MTPA Throughput Capacity in Unchabali Iron… — cleared for impact study, 2.9 km away
- Application for Change in Land Use Pattern Over an Area of 43.281 Ha. From… — not approved, 2.9 km away
- Proposed 0.6 MTPA Iron Ore Pellet Plant & 5 Nos. (4W+1S) Producer Gas Plant of… — environmental approval granted, 3 km away
- Proposed 0.6 MTPA Iron Ore Pellet Plant & 5 Nos. (4W+1S) Producer Gas Plant of… — lapsed, 3 km away
- Proposed Iron ore beneficiation plant of M/s Shree Sindhuja Steels private… — cleared for impact study, 3.1 km away
More from Mgm Minerals Limited in Kendujhar
About this information
This page is compiled from publicly available approval records and rewritten in plain language. Statuses can change between our updates, so check with the authority before making decisions. Spotted a mistake? Tell us.