One of 2 filings for this project. The project's main page, with every filing and where each stands: Proposed Expansion of Chrome Ore Beneficiation plant from capacity 0.12 MTPA…
Project details
| Status | Lapsed |
|---|---|
| Status since | 29 Jul 2026 |
| Application filed | 30 Jul 2025 |
| Approval sought | Environmental approval |
| Application type | Expansion |
| Sector | Mining |
| Applicant | Adish Minerals Private Limited |
| Land area | 13.4 acres (5.4 ha) |
| Project cost | ₹14.3 crore |
| Village / locality | B>Unsamuli |
| Taluk / tehsil | Badachana |
| District | Jajapur |
| State | Odisha |
| Location from | Site boundary on record |
| Our reference | WID-OR-02753 |
All filings for this project
This project has 2 applications on record. Each is a separate step (an impact study, an approval, an expansion…):
| Filing | Status | Land | Cost |
|---|---|---|---|
| Expansion filed 30 Jul 2025 (this page) | Lapsed | 13.4 acres | ₹14.3 crore |
| Early planning filed 29 Dec 2023 | Cleared for impact study | 13.4 acres | ₹14.3 crore |
In context
214 applications in Jajapur since January 2022 are in the same category (Mining): 131 approved, 18 filed or under review, and 65 withdrawn, lapsed or rejected. The approved ones took a median of 3 months from filing to approval. At 13.4 acres, this one is larger than 73% of them.
No other mining lease on record is within 500 m of this site; 1 has applied within 5 km.
Where it is
B>Unsamuli, Badachana, Jajapur, Odisha. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.
Other projects nearby
- Proposed Expansion of Chrome Ore Beneficiation plant from capacity 0.12 MTPA… — cleared for impact study, 0 m away
- 0.12 Million TPA(Throughput) Chrome Ore beneficiation Plant at mouza Baragada… — environmental approval granted, 4.9 km away
- 0.12 Million TPA(Throughput) Chrome Ore beneficiation Plant at mouza Baragada… — cleared for impact study, 4.9 km away
- To Establish 19,500 TPA (Throughput) Chrome Ore Beneficiation & 24,000 TPA… — environmental approval granted, 5.8 km away
- To Establish 19,500 TPA (Throughput) Chrome Ore Beneficiation & 24,000 TPA… — cleared for impact study, 5.8 km away
- To Establish 19,500 TPA Chrome Ore Beneficiation & 24,000 TPA Chromes… — not approved, 5.8 km away
- To Establish 19,500 TPA Chrome Ore Beneficiation & 24,000 TPA Chromes… — returned to applicant, 5.8 km away
- New Chrome Ore Beneficiation (COB) Plant of capacity 60000 TPA (Throughput)… — cleared for impact study, 6.4 km away