Project details
| Official title | Expansion of Existing Integrated Steel Plant of Ninl From 0.981 Mtpa to 9.5 Mtpa Crude Steel at Kalinganagar Industrial Complex, in Jajpur District of Odisha |
|---|---|
| Status | Environmental approval granted |
| Status since | 24 Feb 2026 |
| Application filed | 28 Oct 2025 |
| Approval sought | Environmental approval |
| Application type | Expansion |
| Sector | Industry |
| Applicant | Neelachal Ispat Nigam Limited |
| Land area | 2,538.6 acres (1,027.3 ha) |
| Project cost | ₹73,869 crore |
| Village / locality | Khurunti |
| Taluk / tehsil | Kalinganagar |
| District | Jajapur |
| State | Odisha |
| Location from | Site boundary on record |
| Our reference | WID-OR-02901 |
In context
56 applications in Jajapur since January 2022 are in the same category (Industry): 27 approved, 15 filed or under review, and 14 withdrawn, lapsed or rejected. The approved ones took a median of 3 months from filing to approval. At 2,538.6 acres, this one is larger than 82% of them.
15 other applications of any kind have been filed within 5 km of this site since January 2022.
Where it is
Khurunti, Kalinganagar, Jajapur, Odisha. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.
Close to Tata Steel Plans a 10-Million-Tonne Expansion at Kalinganagar, Odisha (3.6 km away).
Other projects nearby
- Expansion of Existing Integrated Steel Plant of Ninl From 0.981 Mtpa to 9.5… — returned to applicant, 0 m away
- Transfer of existing Environmental Clearance of Neelachal Ispat Nigam Limited,… — environmental approval granted, 0 m away
- Expansion of Existing Integrated Steel Plant of Ninl From 0.981 Mtpa to 9.5… — cleared for impact study, 0 m away
- Proposed enhancement in production of Hot Metal in Blast Furnace from 1.004… — initial checks, 0 m away
- Transfer of existing Environmental Clearance of Neelachal Ispat Nigam Limited,… — environmental approval granted, 100 m away
- Transfer of ownership of existing Forest Clearance of Neelachal Ispat Nigam… — more information requested, 100 m away
- Change in Land Use of 755.495 Ha. of Forest Land Under Kataka Forest Division… — under forest review, 150 m away
- Proposed Addition and Alternation of Shed 01 and Proposed Shed 03, Admin Block… — lapsed, 2.2 km away
More from Neelachal Ispat Nigam Limited in Jajapur
- Change in Land Use of 755.495 Ha. of Forest Land Under Kataka Forest Division… — under forest review
- Expansion of Existing Integrated Steel Plant of Ninl From 0.981 Mtpa to 9.5… — returned to applicant
- Transfer of existing Environmental Clearance of Neelachal Ispat Nigam Limited,… — environmental approval granted
- Transfer of ownership of existing Forest Clearance of Neelachal Ispat Nigam… — more information requested
- Transfer of existing Environmental Clearance of Neelachal Ispat Nigam Limited,… — environmental approval granted
- Expansion of Existing Integrated Steel Plant of Ninl From 0.981 Mtpa to 9.5… — cleared for impact study
8 Neelachal Ispat Nigam projects in Jajapur
All 12 Neelachal Ispat Nigam projects across India
About this information
This page is compiled from publicly available approval records and rewritten in plain language. Statuses can change between our updates, so check with the authority before making decisions. Spotted a mistake? Tell us.