Project details
| Official title | Proposal for Grant of Ec of Sianbahal Stone Quarry Based on Modified Mining Plan(Without Blasting) Over an Area 12 Acres Or 4.856 Hectare in Village Sianbahal of Koira Tahasil, Dist- Sundargarh |
|---|---|
| Status | Environmental approval granted |
| Status since | 6 Nov 2026 |
| Application filed | 9 Sept 2026 |
| Approval sought | Environmental approval |
| Application type | New project |
| Sector | Mining |
| Applicant | Jyotin Sahoo |
| Land area | 28.7 acres (11.6 ha) |
| Project cost | ₹25 lakh |
| Village / locality | Sianbahal |
| Taluk / tehsil | Kamarposh Balang |
| District | Sundargarh |
| State | Odisha |
| Location from | Site boundary on record |
| Our reference | WID-OR-03417 |
In context
310 applications in Sundargarh since January 2022 are in the same category (Mining): 161 approved, 55 filed or under review, and 94 withdrawn, lapsed or rejected. The approved ones took a median of 3 months from filing to approval. At 28.7 acres, this one is larger than 50% of them.
1 other mining lease has applied within 500 m of this site; together with this one they cover 40.7 acres. Under India's environmental rules, mining leases less than 500 m apart are assessed together as one cluster, so the combined area can decide which clearance is needed. 1 mining lease has applied within 5 km.
Where it is
Sianbahal, Kamarposh Balang, Sundargarh, Odisha. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.
Other projects nearby
- Obtaining Ec of Sianbahal Stone Quarry Over an Area 12 Acres Or 4.856 Hectare — not approved, 0 m away
- Obtaining Ec of Sianbahal Stone Quarry Over an Area 12 Acres Or 4.856 Hectare — environmental approval granted, 0 m away
- 33KV Power Transmission Line From K-Balanga Pss Grid 33/11KV Electrical… — forest land use approved, 4.1 km away
- Water Pipeline Project which includes Water intake system and Underground… — more information requested, 4.9 km away
- Obtaining EC of Thelakudar Stone Quarry-1 over 10.00Acres or 4.05Hc — lapsed, 6.7 km away
- Obtaining EC of Thelakudar Stone Quarry-2 over 2.30Acres or 0.930Hc — not approved, 6.7 km away
- Grant transfer EC Banko Stone Quarry over an area 12.00Ac or 4.856He — returned to applicant, 8.7 km away
- Grant transfer EC Banko Stone Quarry over an area 12.00Ac or 4.856He — environmental approval granted, 8.7 km away
More from Jyotin Sahoo in Sundargarh
- Obtaining Ec of Sianbahal Stone Quarry Over an Area 12 Acres Or 4.856 Hectare — not approved
- Obtaining Ec of Sianbahal Stone Quarry Over an Area 12 Acres Or 4.856 Hectare — environmental approval granted
About this information
This page is compiled from publicly available approval records and rewritten in plain language. Statuses can change between our updates, so check with the authority before making decisions. Spotted a mistake? Tell us.