| Official title | Construction of the proposed Intake Water Pipeline Corridor for proposed Pottangi Bauxite Mines of Nalco, Damanjodi, koraput District. |
|---|---|
| Status | Forest land use approved |
| Status since | 4 Oct 2024 |
| Application filed | 20 Jul 2023 |
| Approval sought | Forest land use |
| Application type | New project |
| Sector | Pipelines |
| Applicant | National Aluminium Company Limited |
| Land area | 519 acres (210 ha) |
| Forest land | 2.1 acres (0.9 ha) |
| Project cost | ₹14.4 crore |
| Village / locality | Nuagaon |
| Taluk / tehsil | Pottangi |
| District | Koraput |
| State | Odisha |
| Location from | Site boundary on record |
| Our reference | WID-OR-04133 |
In context
2 other applications of any kind have been filed within 5 km of this site since January 2022.
Where it is
Nuagaon, Pottangi, Koraput, Odisha. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.
Other projects nearby
- Proposed Bauxite Mining with production capacity of 3.5 Million TPA by… — environmental approval granted, 2.3 km away
- Application of EC for Production of 1.35 KLD Mohua Flower Based Out Still… — environmental approval granted, 3.5 km away
- Road from Pottangi Bauxite Mines to Alumina Refinery at Damanjodi — forest land use approved, 5.7 km away
- Proposed Bauxite Mining with production capacity of 3.5 Million TPA by… — environmental approval granted, 11.1 km away
- Diversion of 48.2894 Ha of Additional Forest land (13,2933 Ha in Jeypore… — forest land use approved, 14.1 km away
- New Proporal for Fresh Ec of Mania (U. Mania) Stone Quarry-B Over an Area… — not approved, 15.9 km away
- Production Enhancement from 513 Cu.m per Year to 5040 Cu.m per Year from Mania… — environmental approval granted, 15.9 km away
- Transfer of EC of Mania Stone Quarry over an area of 2.50 Acres or 1.011 Ha — environmental approval granted, 16.1 km away
More from National Aluminium Company Limited in Koraput
- Road from Pottangi Bauxite Mines to Alumina Refinery at Damanjodi — forest land use approved
- Amendment to Environmental Clearance for Establishing a New Crusher of… — lapsed
- Amendment to Environmental Clearance for Establishing a New Crusher of… — cleared for impact study
All 4 National Aluminium Company projects across India
About this information
This page is compiled from publicly available approval records and rewritten in plain language. Statuses can change between our updates, so check with the authority before making decisions. Spotted a mistake? Tell us.