Project details
| Official title | Proposal for Forest clearance of M/S Misrilall Mines Private Limited for establishment of 30 TPH capacity Chrome Ore Beneficiation Plant having throughput of 198000 TPA and annual Chrome Concentrate production of 97000 TPA based on average grade 30% Cr2O3, At ; Pankapal ,Village; Nimapali, Tehsil: Sukinda ,District: Jajpur |
|---|---|
| Status | Lapsed |
| Status since | 1 Jan 2025 |
| Application filed | 17 May 2023 |
| Approval sought | Forest land use |
| Application type | New project |
| Sector | Industry |
| Applicant | Misrilall Mines PVT LTD |
| Land area | 2.2 acres (0.9 ha) |
| Forest land | 2.2 acres (0.9 ha) |
| Project cost | ₹5 crore |
| Village / locality | Pankapal |
| Taluk / tehsil | Jakhapura |
| District | Jajapur |
| State | Odisha |
| Location from | Site boundary on record |
| Our reference | WID-OR-04199 |
In context
56 applications in Jajapur since January 2022 are in the same category (Industry): 27 approved, 15 filed or under review, and 14 withdrawn, lapsed or rejected. The approved ones took a median of 3 months from filing to approval. At 2.2 acres, this one is smaller than 100% of them.
33 other applications of any kind have been filed within 5 km of this site since January 2022.
Where it is
Pankapal, Jakhapura, Jajapur, Odisha. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.
Close to Tata Steel Plans a 10-Million-Tonne Expansion at Kalinganagar, Odisha (5.1 km away).
Other projects nearby
- Ferro Alloys Plant at Pankpal of M/s Misrilal Mines Private Ltd — not approved, 350 m away
- Expansion of existing Chrome Ore Beneficiation Plant from 1,20,000 TPA to… — lapsed, 1.2 km away
- Cement grinding unit of Capacity 3.0 MTPA by M/S NU Vista Limited — initial checks, 1.9 km away
- Last Mile Connectivity to M/s Brahmani River Pillates Limited — forest land use approved, 2.4 km away
- High Carbon Ferro chrome Manufacturing Unit of Capacity 96,000 TPA & 10 MW… — environmental approval granted, 2.5 km away
- High Carbon Ferro chrome Manufacturing Unit of Capacity 96,000 TPA & 10 MW… — cleared for impact study, 2.5 km away
- Proposal of establishment of 1.5 MTPA of Cement Grinding Unit to Produce PSC,… — environmental approval granted, 2.7 km away
- Expansion of Ferro Alloys plant Submerged Arc Furnace 4x16.5mva existing 1x33mva — environmental approval granted, 2.8 km away
More from Misrilall Mines PVT LTD in Jajapur