Quick answers
What is Industrial project by M/s Modi Sales?
This lapsed industrial project by M/s Modi Sales is in Ludhiana, Ludhiana (West), Punjab. The site covers 1.1 acres.
Who is building it?
The applicant is Modi Sales.
Has it been approved?
No. The application was lapsed on 29 Oct 2024, so it is no longer under consideration.
Where is it?
In Ludhiana, Ludhiana (West), Punjab.
How big is it?
It has a stated cost of ₹8.2 crore and a site of 1.1 acres.
When was it filed?
The application was filed on 19 Jul 2023.
Project details
| Status | Lapsed |
|---|---|
| Status since | 29 Oct 2024 |
| Application filed | 19 Jul 2023 |
| Approval sought | Environmental approval |
| Application type | Early planning |
| Sector | Industry |
| Applicant | Modi Sales |
| Land area | 1.1 acres (0.4 ha) |
| Project cost | ₹8.2 crore |
| Village / locality | Ludhiana |
| Taluk / tehsil | Ludhiana (West) |
| District | Ludhiana |
| State | Punjab |
| Location from | Site boundary on record |
| Our reference | WID-PB-00200 |
In context
98 applications in Ludhiana since January 2022 are in the same category (Industry): 56 approved, 14 filed or under review, and 28 withdrawn, lapsed or rejected. The approved ones took a median of 2 months from filing to approval. At 1.1 acres, this one is smaller than 95% of them.
48 other applications of any kind have been filed within 5 km of this site since January 2022.
Where it is
Ludhiana, Ludhiana (West), Punjab. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.
Other projects nearby
- Hero Steels Limited located at Hero Nagar, Sua Road, Ludhiana having capacity… — environmental approval granted, 500 m away
- Hero Steels Limited located at Hero Nagar, Sua Road, Ludhiana having capacity… — cleared for impact study, 500 m away
- MS/HSD Regular Retail Outlet Dealership of Hindustan Petroleum Corporation… — forest land use approved, 550 m away
- Existing Steel Manufacturing Unit M/s Aarti Steel Limited (Rolling Mill… — cleared for impact study, 600 m away
- Existing Steel Manufacturing Unit M/s Aarti Steel Limited (Rolling Mill… — lapsed, 600 m away
- Existing Steel Manufacturing Unit M/s Aarti Steel Limited (Rolling Mill… — cleared for impact study, 600 m away
- Expansion of Existing Electric Arc Furnace Capacity From 30 Tph to 35.5 Tph… — cleared for impact study, 800 m away
- Expansion of Existing Electric Arc Furnace Capacity From 32.3 Tph to 35.5 Tph… — lapsed, 800 m away
About this information
This page is compiled from publicly available approval records and rewritten in plain language. Statuses can change between our updates, so check with the authority before making decisions. Spotted a mistake? Tell us.