M/s Jainco Enterprises Pvt. Ltd., (REFERENCE NO. 20221000062932),MASONARY STONE MINING PROJECT is an approved mining project in Dhundliya, Aklera, Jhalawar, Rajasthan. The site covers 2.2 acres.
Who is building it?
The applicant is Jainco Enterprises Private Limited.
Has it been approved?
Yes. Its status is “Environmental approval granted” (since 13 Sept 2023), as of 27 Nov 2026.
Where is it?
In Dhundliya, Aklera, Jhalawar, Rajasthan.
How big is it?
It has a stated cost of ₹1 crore and a site of 2.2 acres.
When was it filed?
The application was filed on 13 Sept 2023.
Project details
| Status | Environmental approval granted |
|---|---|
| Status since | 13 Sept 2023 |
| Application filed | 13 Sept 2023 |
| Approval sought | Environmental approval |
| Application type | New project |
| Sector | Mining |
| Applicant | Jainco Enterprises Private Limited |
| Land area | 2.2 acres (0.9 ha) |
| Project cost | ₹1 crore |
| Village / locality | Dhundliya |
| Taluk / tehsil | Aklera |
| District | Jhalawar |
| State | Rajasthan |
| Location from | Site boundary on record |
| Our reference | WID-RJ-00709 |
In context
140 applications in Jhalawar since January 2022 are in the same category (Mining): 91 approved, 22 filed or under review, and 27 withdrawn, lapsed or rejected. The approved ones took a median of 2 months from filing to approval. At 2.2 acres, this one is smaller than 95% of them.
No other mining lease on record has applied within 5 km of this site.
Where it is
Dhundliya, Aklera, Jhalawar, Rajasthan. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.
Other projects nearby
- 132 kV S/C Transmission Line from Proposed 220kV GSS Aklera (Jhalawar) to 132… — forest land use approved, 2.1 km away
- Widening & Strengthening Kalmodiya Manoharthana Rajgarh road km 8/900 to… — more information requested, 2.4 km away
- Chhapi Extension From Chhapi Dam & Gulandi Water Supply Project — lapsed, 4.3 km away
- Smt. Arti Choudhary, M.L.No.02/2006, Re-appraisal of Environmental Clearance… — environmental approval granted, 6.1 km away
- Shree Sudeep Jethi, Re-appraisal of Environment Clearance granted by DEIAA to… — environmental approval granted, 6.1 km away
- Shri Sudeep Jethi,Masonary Stone Mining Project M.L. No. - 15/2005 — environmental approval granted, 6.1 km away
- M/s SS-RM-JV, Ref. No. 20231000093675, Masonary Stone Mining Project — environmental approval granted, 6.7 km away
- M/s SS-RM-JV, Ref. No. 20221000093675, Masonary Stone Mining Project — lapsed, 6.7 km away
About this information
This page is compiled from publicly available approval records and rewritten in plain language. Statuses can change between our updates, so check with the authority before making decisions. Spotted a mistake? Tell us.