Quick answers
What is this project?
Shree Sudeep Jethi, Re-appraisal of Environment Clearance granted by DEIAA to SEIAA in compliance of MoEF & CC O.M. dated 28/04/2023 & Hon'ble NGT order dated 07/12/2022 ,M.L. No.: -15/2005, Masonary Stone Project is an approved mining project in Uni, Aklera, Jhalawar, Rajasthan. The site covers 3.7 acres.
Who is building it?
The applicant is Sudeep Jethi.
Has it been approved?
Yes. Its status is “Environmental approval granted” (since 24 Feb 2025), as of 27 Nov 2026.
Where is it?
In Uni, Aklera, Jhalawar, Rajasthan.
How big is it?
It has a stated cost of ₹60 lakh and a site of 3.7 acres.
When was it filed?
The application was filed on 24 Sept 2024.
Project details
| Status | Environmental approval granted |
|---|---|
| Status since | 24 Feb 2025 |
| Application filed | 24 Sept 2024 |
| Approval sought | Environmental approval |
| Application type | New project |
| Sector | Mining |
| Applicant | Sudeep Jethi |
| Land area | 3.7 acres (1.5 ha) |
| Project cost | ₹60 lakh |
| Village / locality | Uni |
| Taluk / tehsil | Aklera |
| District | Jhalawar |
| State | Rajasthan |
| Location from | Site boundary on record |
| Our reference | WID-RJ-07009 |
In context
140 applications in Jhalawar since January 2022 are in the same category (Mining): 91 approved, 22 filed or under review, and 27 withdrawn, lapsed or rejected. The approved ones took a median of 2 months from filing to approval. At 3.7 acres, this one is smaller than 58% of them.
1 other mining lease has applied within 500 m of this site; together with this one they cover 6.2 acres. Under India's environmental rules, mining leases less than 500 m apart are assessed together as one cluster, so the combined area can decide which clearance is needed. 1 mining lease has applied within 5 km.
Where it is
Uni, Aklera, Jhalawar, Rajasthan. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.
Other projects nearby
- Shri Sudeep Jethi,Masonary Stone Mining Project M.L. No. - 15/2005 — environmental approval granted, 0 m away
- Smt. Arti Choudhary, M.L.No.02/2006, Re-appraisal of Environmental Clearance… — environmental approval granted, 100 m away
- Shri Ji Organic Fertilisers — lapsed, 3.6 km away
- M/s Jainco Enterprises Pvt. Ltd., (REFERENCE NO. 20221000062932),MASONARY… — environmental approval granted, 6.1 km away
- Widening & Strengthening Kalmodiya Manoharthana Rajgarh road km 8/900 to… — more information requested, 6.6 km away
- 132 kV S/C Transmission Line from Proposed 220kV GSS Aklera (Jhalawar) to 132… — forest land use approved, 8.2 km away
- Chhapi Extension From Chhapi Dam & Gulandi Water Supply Project — lapsed, 8.7 km away
- Shri Nasiruddin ML No. 68/1993 Minerals Sand Stone & Masonary Stone — environmental approval granted, 11 km away
More from Sudeep Jethi in Jhalawar
- Shri Sudeep Jethi,Masonary Stone Mining Project M.L. No. - 15/2005 — environmental approval granted
About this information
This page is compiled from publicly available approval records and rewritten in plain language. Statuses can change between our updates, so check with the authority before making decisions. Spotted a mistake? Tell us.