Quick answers
What is this project?
"Reappraisal of the EC granted by DEIAA Jodhpur, for Limestone Mining Project, M.L. No. 187/1995" is a lapsed mining project in Boroonda, Pipar Shahar, Jodhpur, Rajasthan. The site covers 12.4 acres.
Who is building it?
The applicant is Nand Kishor Agarwal.
Has it been approved?
No. The application was lapsed on 29 Oct 2024, so it is no longer under consideration.
Where is it?
In Boroonda, Pipar Shahar, Jodhpur, Rajasthan.
How big is it?
It has a stated cost of ₹1 crore and a site of 12.4 acres.
When was it filed?
The application was filed on 31 May 2024.
Project details
| Status | Lapsed |
|---|---|
| Status since | 29 Oct 2024 |
| Application filed | 31 May 2024 |
| Approval sought | Environmental approval |
| Application type | New project |
| Sector | Mining |
| Applicant | Nand Kishor Agarwal |
| Land area | 12.4 acres (5 ha) |
| Project cost | ₹1 crore |
| Village / locality | Boroonda |
| Taluk / tehsil | Pipar Shahar |
| District | Jodhpur |
| State | Rajasthan |
| Location from | Site boundary on record |
| Our reference | WID-RJ-13414 |
In context
11,954 applications in Jodhpur since January 2022 are in the same category (Mining): 4,406 approved, 210 filed or under review, and 7,338 withdrawn, lapsed or rejected. The approved ones took a median of 7 months from filing to approval. At 12.4 acres, this one is larger than 99% of them.
1 other mining lease has applied within 500 m of this site; together with this one they cover 24.7 acres. Under India's environmental rules, mining leases less than 500 m apart are assessed together as one cluster, so the combined area can decide which clearance is needed. 11 mining leases have applied within 5 km.
Where it is
Boroonda, Pipar Shahar, Jodhpur, Rajasthan. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.
Other projects nearby
- Re-appraisal of Environment Clearance granted by DEIAA to SEIAA in compliance… — environmental approval granted, 50 m away
- Transfer of Environmental Clearance (from M/s Ghanshyam Limestone Company to… — environmental approval granted, 1.6 km away
- Proposed Enhancement in Existing Production Capacity from 25000 TPA to 391548… — lapsed, 1.6 km away
- Re-Appraisal of the Lime Stone mining project ML. No.-11/2012, Area-4.00 Ha,… — lapsed, 2.7 km away
- Borunda Limestone Mine (Minor Mineral) (M.L. No. 134/1996) over an area 4.9998… — lapsed, 2.8 km away
- Regarding Transfer / Name Change in the Environment Clearance Letter of… — environmental approval granted, 4.1 km away
- Regarding Transfer of EC of our Existing Lime Stone (Minor Mineral) Mining… — environmental approval granted, 4.1 km away
- "Limestone Mining Project has been transferring via Shri Virendra Shrivastav… — lapsed, 4.3 km away
More from Nand Kishor Agarwal in Jodhpur
- Re-appraisal of Environment Clearance granted by DEIAA to SEIAA in compliance… — environmental approval granted
About this information
This page is compiled from publicly available approval records and rewritten in plain language. Statuses can change between our updates, so check with the authority before making decisions. Spotted a mistake? Tell us.