Quick answers
What is this project?
Proposed expansion of Gas Processing Complex (GPC) from 1 MMSCMD to 1.5 MMSCMD within the existing Dandewala (DND) block of 250 Sq.km is an approved mining project in Tanot, Jaisalmer, Rajasthan. The site covers 61,776.3 acres.
Who is building it?
The applicant is Oil India LTD Rajasthan Project.
Has it been approved?
Yes. Its status is “Environmental approval granted” (since 7 Sept 2026), as of 27 Nov 2026.
Where is it?
In Tanot, Jaisalmer, Rajasthan.
How big is it?
It has a stated cost of ₹172 crore and a site of 61,776.3 acres.
When was it filed?
The application was filed on 11 May 2026.
Project details
| Status | Environmental approval granted |
|---|---|
| Status since | 7 Sept 2026 |
| Application filed | 11 May 2026 |
| Approval sought | Environmental approval |
| Application type | Expansion |
| Sector | Mining |
| Applicant | Oil India LTD Rajasthan Project |
| Land area | 61,776.3 acres (25,000 ha) |
| Project cost | ₹172 crore |
| Village / locality | Tanot |
| Taluk / tehsil | Jaisalmer |
| District | Jaisalmer |
| State | Rajasthan |
| Location from | Site area on record |
| Our reference | WID-RJ-33372 |
All filings for this project
This project has 2 applications on record. Each is a separate step (an impact study, an approval, an expansion…):
| Filing | Status | Land | Cost |
|---|---|---|---|
| Expansion filed 11 May 2026 (this page) | Environmental approval granted | 61,776.3 acres | ₹172 crore |
| Early planning filed 2 Nov 2022 | Cleared for impact study | 61,776.3 acres | ₹172 crore |
In context
575 applications in Jaisalmer since January 2022 are in the same category (Mining): 231 approved, 103 filed or under review, and 241 withdrawn, lapsed or rejected. The approved ones took a median of 7 months from filing to approval. At 61,776.3 acres, this one is larger than 99% of them.
No other mining lease on record has applied within 5 km of this site.
Where it is
Tanot, Jaisalmer, Rajasthan. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.
Other projects nearby
- Proposed expansion of Gas Processing Complex (GPC) from 1 MMSCMD to 1.5 MMSCMD… — cleared for impact study, 0 m away
- Proposed Onshore Developmental drilling of 12 no. s of wells in… — cleared for impact study, 28.7 km away
- Drilling of 25 Nos. wells in 885.35 Sq. Km area of Jaiselmer Basin (comprises… — returned to applicant, 34.6 km away
- Ec for Oil and Gas Exploration & Appraisal for Drilling of 02 Exploratory… — lapsed, 34.6 km away
- Onshore Development and Production of Oil & Gas from 20 Wells in 4 ML… — cleared for impact study, 35.3 km away
- EC for Drilling of 01 Exploratory Well CWAC in south kharatar (Part A and Part… — lapsed, 48 km away
- Onshore Oil and Gas Exploration and Appraisal in RJ-ONHP-2018/1 block (417.44… — lapsed, 53.9 km away
- 400 kV S/C Overhead Transmission Line from proposed 400KV PSS of M/s Adani… — more information requested, 54.8 km away
3 Oil India (OIL) projects in Jaisalmer
All 97 Oil India (OIL) projects across India
About this information
This page is compiled from publicly available approval records and rewritten in plain language. Statuses can change between our updates, so check with the authority before making decisions. Spotted a mistake? Tell us.