| Official title | Proposed 300 KLPD Grain based Ethanol Plant along with 6.5 MW Cogeneration Power Plant at Village Jalodi, Tehsil Talera, District Bundi, Rajasthan by M/s. Vidya Green Ventures Private Limited |
|---|---|
| Status | Environmental approval granted |
| Status since | 23 Jun 2026 |
| Application filed | 21 May 2026 |
| Approval sought | Environmental approval |
| Application type | Amendment |
| Sector | Industry |
| Applicant | Vidya Green Ventures Private Limited |
| Land area | 16.8 acres (6.8 ha) |
| Project cost | ₹353.1 crore |
| Village / locality | Jalodi |
| Taluk / tehsil | Talera |
| District | Bundi |
| State | Rajasthan |
| Location from | Site boundary on record |
| Our reference | WID-RJ-34716 |
All filings for this project
This project has 3 applications on record. Each is a separate step (an impact study, an approval, an expansion…):
| Filing | Status | Land | Cost |
|---|---|---|---|
| Amendment filed 21 May 2026 (this page) | Environmental approval granted | 16.8 acres | ₹353.1 crore |
| Amendment filed 5 May 2026 | Withdrawn | 16.8 acres | ₹353.1 crore |
| New project filed 13 Oct 2023 | Environmental approval granted | 22 acres | ₹353.1 crore |
In context
18 applications in Bundi since January 2022 are in the same category (Industry): 12 approved, 3 filed or under review, and 3 withdrawn, lapsed or rejected. The approved ones took a median of 3 months from filing to approval. At 16.8 acres, this one is smaller than 100% of them.
8 other applications of any kind have been filed within 5 km of this site since January 2022.
Where it is
Jalodi, Talera, Bundi, Rajasthan. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.
Other projects nearby
- Proposed 300 KLPD Grain based Ethanol Plant by M/s. Vidya Green Ventures… — withdrawn, 0 m away
- Proposed 300 KLPD Grain based Ethanol Plant by M/s. Vidya Green Ventures… — environmental approval granted, 50 m away
- Greenfield Project of Grain Based Distillery Plant of 180 KLD by M/s Oasis… — environmental approval granted, 600 m away
- Expansion of Grain based Distillery Plant from 180 KLPD (Ethanol) to 380 KLPD… — environmental approval granted, 650 m away
- Expansion of Grain based Distillery Plant from 180 KLPD (Ethanol) to 380 KLPD… — cleared for impact study, 650 m away
- Proposed Industrial Shed Project for Manufacturing of Beverage Products — environmental approval granted, 1.8 km away
- Proposed 190 KLD Grain based Distillery — environmental approval granted, 3.2 km away
- Proposed 190 KLD Grain based Distillery — cleared for impact study, 3.2 km away
All 3 Vidya Green Ventures projects across India