Fatehgarh-III (Section-2) PS -Barmer-I PS 400 kV D/C Transmission Line (Quad) over head Transmission line by PowerGrid Barmer I Transmission Limited

Fatehgarh-III (Section-2) PS -Barmer-I PS 400 kV D/C Transmission Line (Quad) over head Transmission line by PowerGrid Barmer I Transmission Limited is a lapsed power project in Adarsh Basti Nand, Barmer, Rajasthan. The site covers 4,857.1 acres. Its stated project cost is ₹132.2 crore. As of 27 Nov 2026, its status is “Lapsed” (since 12 Nov 2025).

See it on the live map All projects in Barmer

Data last refreshed 27 Nov 2026, 6:36 am IST. We check for new filings and status changes twice a day.

Quick answers

What is this project?

Fatehgarh-III (Section-2) PS -Barmer-I PS 400 kV D/C Transmission Line (Quad) over head Transmission line by PowerGrid Barmer I Transmission Limited is a lapsed power project in Adarsh Basti Nand, Barmer, Rajasthan. The site covers 4,857.1 acres.

Who is building it?

The applicant is Powergrid Barmer I Transmission Limited.

Has it been approved?

No. The application was lapsed on 12 Nov 2025, so it is no longer under consideration.

Where is it?

In Adarsh Basti Nand, Barmer, Rajasthan.

How big is it?

It has a stated cost of ₹132.2 crore; a site of 4,857.1 acres and 28.4 acres (11.5 ha) of forest land.

When was it filed?

The application was filed on 6 May 2025.

Project details

Official titleConstruction of Fatehgarh-III (Section-2) PS -Barmer-I PS 400 kV D/C Transmission Line (Quad) over head Transmission line under the Transmission Scheme in Transmission system for Evacuation of power from Rajasthan REZ Ph-IV (Part-2: 5.5 GW) (Jaisalmer/Barmer Complex) Part -F by PowerGrid Barmer I Transmission Limited
StatusLapsed
Status since12 Nov 2025
Application filed6 May 2025
Approval soughtForest land use
Application typeNew project
SectorPower
ApplicantPowergrid Barmer I Transmission Limited
Land area4,857.1 acres (1,965.6 ha)
Forest land28.4 acres (11.5 ha)
Project cost₹132.2 crore
Village / localityAdarsh Basti Nand
Taluk / tehsilBarmer
DistrictBarmer
StateRajasthan
Location fromSite boundary on record
Our referenceWID-RJ-35959

In context

24 applications in Barmer since January 2022 are in the same category (Power): 8 approved, 13 filed or under review, and 3 withdrawn, lapsed or rejected. The approved ones took a median of 12 months from filing to approval. At 4,857.1 acres, this one is larger than 83% of them.

15 other applications of any kind have been filed within 5 km of this site since January 2022.

Where it is

Adarsh Basti Nand, Barmer, Rajasthan. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.

Other projects nearby

More from Powergrid Barmer I Transmission Limited in Barmer

About this information

This page is compiled from publicly available approval records and rewritten in plain language. Statuses can change between our updates, so check with the authority before making decisions. Spotted a mistake? Tell us.