Forest land use approvedPower · Barmer, Rajasthan

Barmer-I PS-Sirohi PS 765kV D/C Transmission Line Overhead Transmission line by PowerGrid Barmer-I Transmission Limited

Barmer-I PS-Sirohi PS 765kV D/C Transmission Line Overhead Transmission line by PowerGrid Barmer-I Transmission Limited is an approved power project in Adarsh Undkha, Barmer, Rajasthan. The site covers 7,438 acres. Its stated project cost is ₹935 crore. As of 27 Nov 2026, its status is “Forest land use approved” (since 6 May 2026).

See it on the live map All projects in Barmer

Data last refreshed 27 Nov 2026, 6:36 am IST. We check for new filings and status changes twice a day.

Quick answers

What is this project?

Barmer-I PS-Sirohi PS 765kV D/C Transmission Line Overhead Transmission line by PowerGrid Barmer-I Transmission Limited is an approved power project in Adarsh Undkha, Barmer, Rajasthan. The site covers 7,438 acres.

Who is building it?

The applicant is Powergrid Barmer I Transmission Limited.

Has it been approved?

Yes. Its status is “Forest land use approved” (since 6 May 2026), as of 27 Nov 2026.

Where is it?

In Adarsh Undkha, Barmer, Rajasthan.

How big is it?

It has a stated cost of ₹935 crore; a site of 7,438 acres and 2,410 m² of forest land.

When was it filed?

The application was filed on 1 May 2025.

Project details

Official titleConstruction of Barmer-I PS-Sirohi PS 765kV D/C Transmission Line Overhead Transmission line under the Transmission Scheme in Transmission system for Evacuation of power from Rajasthan REZ Ph-IV (Part-2: 5.5 GW) (Jaisalmer/Barmer Complex) Part -F by PowerGrid Barmer-I Transmission Limited
StatusForest land use approved
Status since6 May 2026
Application filed1 May 2025
Approval soughtForest land use
Application typeNew project
SectorPower
ApplicantPowergrid Barmer I Transmission Limited
Land area7,438 acres (3,010 ha)
Forest land2,410 m²
Project cost₹935 crore
Village / localityAdarsh Undkha
Taluk / tehsilBarmer
DistrictBarmer
StateRajasthan
Location fromSite boundary on record
Our referenceWID-RJ-35883

In context

24 applications in Barmer since January 2022 are in the same category (Power): 8 approved, 13 filed or under review, and 3 withdrawn, lapsed or rejected. The approved ones took a median of 12 months from filing to approval. At 7,438 acres, this one is larger than 91% of them.

Where it is

Adarsh Undkha, Barmer, Rajasthan. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.

Other projects nearby

More from Powergrid Barmer I Transmission Limited in Barmer

About this information

This page is compiled from publicly available approval records and rewritten in plain language. Statuses can change between our updates, so check with the authority before making decisions. Spotted a mistake? Tell us.