Quick answers
What is this project?
Upgradation to 4 Lane With Paved Shoulders from Existing KM 58/245 to 108/600 of NH-8(Beawar -Gomti Section)on EPC Mode in the State of Rajasthan is an approved road project in Bhojpura, Beawar, Ajmer, Rajasthan. It seeks 14.1 acres of forest land.
Who is building it?
The applicant is Ministry of Road Transport & Highways.
Has it been approved?
Yes. Its status is “Forest land use approved” (since 17 Apr 2026), as of 27 Nov 2026.
Where is it?
In Bhojpura, Beawar, Ajmer, Rajasthan.
How big is it?
It has a stated cost of ₹379.2 crore and 14.1 acres (5.7 ha) of forest land.
When was it filed?
The application was filed on 7 Mar 2023.
Project details
| Status | Forest land use approved |
|---|---|
| Status since | 17 Apr 2026 |
| Application filed | 7 Mar 2023 |
| Approval sought | Forest land use |
| Application type | New project |
| Sector | Roads & highways |
| Applicant | Ministry of Road Transport & Highways |
| Forest land | 14.1 acres (5.7 ha) |
| Project cost | ₹379.2 crore |
| Village / locality | Bhojpura |
| Taluk / tehsil | Beawar |
| District | Ajmer |
| State | Rajasthan |
| Location from | Site boundary on record |
| Our reference | WID-RJ-36284 |
In context
18 applications in Ajmer since January 2022 are in the same category (Roads & highways): 3 approved, 6 filed or under review, and 7 withdrawn, lapsed or rejected.
2 other applications of any kind have been filed within 5 km of this site since January 2022.
Where it is
Bhojpura, Beawar, Ajmer, Rajasthan. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.
Other projects nearby
- Re-Appraisal of EC granted from DEIAA, Ajmer (Raj.) for Existing Quartz &… — environmental approval granted, 650 m away
- EC for Expansion of Quartz & Feldspar (Minor Mineral) Mining project [M.L.… — withdrawn, 650 m away
- Wildlife Clearance for Existing Road Repair Work on Gafa Approach Road to… — decision issued, 12.6 km away
- Wildlife Clearance for Existing Road Repair Work on Jodhpur vinakiya Sojat… — more information requested, 13 km away
- Existing Quartz & Feldspar (Major Minral) Mining Project, Expansion In… — cleared for impact study, 13.9 km away
- Existing Quartz & Feldspar Mining Project, Expansion In Production Capacity… — lapsed, 13.9 km away
- Permission for Laying Underground Ofc Along Existing Road Located Between Bhim… — lapsed, 14.1 km away
- Reappraisal of the EC granted by DEIAA Ajmer for Quartz & Feldspar Mining… — lapsed, 14.3 km away
More from Ministry of Road Transport & Highways in Ajmer
- Upgradation of 2 Lane to 4 Lane With Paved Shoulder of NH-79 (New NH-448) From… — forest land use approved
About this information
This page is compiled from publicly available approval records and rewritten in plain language. Statuses can change between our updates, so check with the authority before making decisions. Spotted a mistake? Tell us.