Quick answers
What is this project?
Rectification of 05 no. blackspots viz "RIICO Khara Industrial Area" from Ch. 18+800 to 19+300, "Jamasar Bus Stand" from Ch. 27+800 to 28+300, "Lunkaransar" from Ch. 72+800 to 73+300, "Mokalsar" from Ch. 131+000 to 131+500 and "Premnagar Fata" from Ch. 134+500 to 135+000 of NH-62 (Bikaner – Suratgarh section) under Road Safety Annual Plan 2024-25 in the State of Rajasthan on EPC Mode is a proposed road project in Mokalsar, Suratgarh, Ganganagar, Rajasthan. The site covers 64.6 acres.
Who is building it?
The applicant is Ministry of Road Tranport and Highways Government of India New Delhi.
Has it been approved?
Not yet. The application is still under review: its status is “More information requested”, as of 27 Nov 2026.
Where is it?
In Mokalsar, Suratgarh, Ganganagar, Rajasthan.
How big is it?
It has a stated cost of ₹52.8 crore; a site of 64.6 acres and 18 acres (7.3 ha) of forest land.
When was it filed?
The application was filed on 10 Nov 2025.
Project details
| Status | More information requested |
|---|---|
| Status since | 16 Nov 2026 |
| Application filed | 10 Nov 2025 |
| Approval sought | Forest land use |
| Application type | New project |
| Sector | Roads & highways |
| Applicant | Ministry of Road Tranport and Highways Government of India New Delhi |
| Land area | 64.6 acres (26.2 ha) |
| Forest land | 18 acres (7.3 ha) |
| Project cost | ₹52.8 crore |
| Village / locality | Mokalsar |
| Taluk / tehsil | Suratgarh |
| District | Ganganagar |
| State | Rajasthan |
| Location from | Site boundary on record |
| Our reference | WID-RJ-36629 |
In context
9 applications in Ganganagar since January 2022 are in the same category (Roads & highways): 6 approved, 3 filed or under review, and 0 withdrawn, lapsed or rejected. The approved ones took a median of 2.7 years from filing to approval.
Where it is
Mokalsar, Suratgarh, Ganganagar, Rajasthan. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.
Other projects nearby
- Approach Road for Proposed Hindustan Petroleum Corporation Ltd. Retail Outlet… — forest land use approved, 71.6 km away
- Construction for LILO of 132kV S/C Srivijaynagar-Anoopgarh Transmission Line… — more information requested, 79.2 km away
- "Construction of Underground 132KV S/C Transmission Line using 132 KV 400 sq.… — forest land use approved, 79.6 km away
- Full Title of the Project Proposed for Diversion 221.40ha. for "construction /… — forest land use approved, 81.1 km away
- Approach Road for Proposed Indian Oil Corporation Limited Retail Outlet on BRO… — forest land use approved, 83.9 km away
- Proposed 180 KLD Grain based Distillery — environmental approval granted, 89 km away
- Proposed 180 KLD Grain based Distillery — environmental approval granted, 89 km away
- Proposed 180 KLD Grain based Distillery — cleared for impact study, 89 km away
More from Ministry of Road Tranport and Highways Government of India New Delhi in Ganganagar
- Diversion of Forest Land for construction of Two lane to Four lane for… — in-principle approval, conditions pending
All 46 Ministry of Road Tranport and Highways Government of India New Delhi projects across India