Project details
| Status | Under wildlife review |
|---|---|
| Status since | 13 Nov 2026 |
| Application filed | 26 Oct 2026 |
| Approval sought | Wildlife review |
| Application type | New project |
| Sector | Buildings & townships |
| Applicant | Public Health Engineering Deparment Rajasthan |
| Land area | 162.7 acres (65.9 ha) |
| Project cost | ₹476.5 crore |
| Village / locality | Ghata Ka Barana |
| Taluk / tehsil | Indragarh |
| District | Bundi |
| State | Rajasthan |
| Location from | Site boundary on record |
| Our reference | WID-RJ-37365 |
In context
17 applications in Bundi since January 2022 are in the same category (Buildings & townships): 1 approved, 12 filed or under review, and 2 withdrawn, lapsed or rejected. At 162.7 acres, this one is larger than 94% of them.
2 other applications of any kind have been filed within 5 km of this site since January 2022.
Where it is
Ghata Ka Barana, Indragarh, Bundi, Rajasthan. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.
Close to ERCPCL Plans an 875-Crore Barrage on the Mej River in Bundi, Rajasthan (14.9 km away).
Other projects nearby
- Execution Testing Commissioning of Transmission Main, RisingMain, ESR, CDS &… — more information requested, 250 m away
- Wildlife Clearance for Proposal for setting up and operating Proposed Indian… — more information requested, 2.4 km away
- Transfer of Environmental Clearance for "Existing Masonry Stone Mining Project… — lapsed, 13.4 km away
- Re-appraisal of Existing Masonry Stone Mining Project, ML. No.- 369/2005,… — returned to applicant, 13.4 km away
- Khari Baran Masonary Stone Mine ( M.L. No. 369/2005) — application filed, 13.4 km away
- Rehabilitation from Core 1 of RVTR Bundi — more information requested, 14.6 km away
- Rehabilitation from Core 1 of RVTR Bundi — lapsed, 14.6 km away
- Diversion of Forest Land for the Construction of Mej Barrage Across Mej River — under forest review, 14.9 km away
More from Public Health Engineering Deparment Rajasthan in Bundi
- Execution Testing Commissioning of Transmission Main, RisingMain, ESR, CDS &… — more information requested
- "Laying of Pipe Line Gararda Water Supply Project to provide FHTC including 10… — decision issued
- "Laying of Pipe Line Gararda Water Supply Project to provide FHTC including 10… — forest land use approved
- Laying of Pipe Line Hindoli-Nainwa Water Supply Project District-Bundi From… — lapsed
- Laying of Pipe Line Hindoli-Nainwa Water Supply Project District-Bundi From… — lapsed
About this information
This page is compiled from publicly available approval records and rewritten in plain language. Statuses can change between our updates, so check with the authority before making decisions. Spotted a mistake? Tell us.