Project details
| Status | Decision issued |
|---|---|
| Status since | 13 May 2024 |
| Application filed | 13 May 2024 |
| Approval sought | Wildlife review |
| Application type | New project |
| Sector | Roads & highways |
| Applicant | Ministry of Defense |
| Land area | 94.2 acres (38.1 ha) |
| Project cost | ₹384.8 crore |
| Village / locality | Lachung |
| Taluk / tehsil | Chungthang |
| District | North District |
| State | Sikkim |
| Location from | Site boundary on record |
| Our reference | WID-SK-00266 |
In context
15 applications in North District since January 2022 are in the same category (Roads & highways): 3 approved, 5 filed or under review, and 6 withdrawn, lapsed or rejected. At 94.2 acres, this one is larger than 69% of them.
Where it is
Lachung, Chungthang, North District, Sikkim. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.
Other projects nearby
- Diversion of Forest Land of 1.0940 Ha for Construction of Cho-Lung Trul-Sum… — lapsed, 7.3 km away
- Diversion of 0.0412 Ha for Forest Land for Laying of Overhead Optical Fiber… — lapsed, 13 km away
- Diversion of 116.1 Ha Forest Land for Widening/Upgradation of Existing Road… — forest land use approved, 13.9 km away
- Diversion of 0.5252 ha of forest land for part construction of Rabom Chu HEP… — forest land use approved, 15.3 km away
- Granting Permission for laying OFC Cable from Chungthang to Lachen under North… — lapsed, 16.2 km away
- Divrsion of Forest Land for Extension of Power Supply to Broder Defence Area… — under forest review, 16.5 km away
- Construction/Improvement on Epc Mode of Existing Road to Nhdl Specification… — lapsed, 17 km away
- Granting Permission for laying OFC Cable through Overhead Methodology from… — lapsed, 17.4 km away
More from Ministry of Defense in North District
- DIVERSION OF FOREST LAND FOR IMPROVEMENT OF MANGAN-SANKLANG ROAD FROM CL-9 TO… — forest land use approved
- Diversion of 116.1 Ha Forest Land for Widening/Upgradation of Existing Road… — forest land use approved
- Diversion of Forest Land Required for Realignment Between Km 80.800 to Km… — lapsed
- Construction/Improvement on Epc Mode of Existing Road to Nhdl Specification… — lapsed