Quick answers
What is this project?
Residential Apartments Construction Project - M/s. Janapriya Engineers Syndicate Private Limited located at Survey Nos. 663(P),667, 668(P), 671(P), Kapra Village, Medchal -Malkajgiri District is an approved residential project in Kapra, Medchal Malkajgiri, Telangana. It plans 2,057 units in 11 towers of up to 14 floors on 12.7 acres.
Who is building it?
The applicant is Janapriya Engineers Syndicate Private Limited.
Has it been approved?
Yes. Its status is “Environmental approval granted” (since 8 Oct 2026), as of 27 Nov 2026.
Where is it?
In Kapra, Medchal Malkajgiri, Telangana.
How big is it?
It has a stated cost of ₹632 crore and a site of 12.7 acres.
When was it filed?
The application was filed on 18 Apr 2026.
Project details
| Status | Environmental approval granted |
|---|---|
| Status since | 8 Oct 2026 |
| Application filed | 18 Apr 2026 |
| Approval sought | Environmental approval |
| Application type | Amendment |
| Sector | Buildings & townships |
| Applicant | Janapriya Engineers Syndicate Private Limited |
| Use | Residential |
| Units | 2,057 |
| Towers | 11 |
| Floors (tallest) | 14 |
| Basements | 2 |
| Parking spaces | 2,338 |
| Land area | 12.7 acres (5.2 ha) |
| Built-up area | 2,55,114 m² (27,46,022 sq ft) |
| Plot area | 51,536 m² (5,54,728 sq ft) |
| Project cost | ₹632 crore |
| Village / locality | Kapra |
| Taluk / tehsil | Kapra |
| District | Medchal Malkajgiri |
| State | Telangana |
| Location from | Site boundary on record |
| Our reference | WID-TG-03691 |
All filings for this project
This project has 2 applications on record. Each is a separate step (an impact study, an approval, an expansion…):
| Filing | Status | Land | Cost |
|---|---|---|---|
| Amendment filed 18 Apr 2026 (this page) | Environmental approval granted | 12.7 acres | ₹632 crore |
| Early planning filed 21 Jan 2026 | Cleared for impact study | 12.7 acres | ₹632 crore |
What the filings say
What is planned
M/s. Janapriya Engineers Syndicate Private Limited proposes to develop a gated community of residential apartments on 5.15 hectares (12.73 acres) of land in Kapra, Telangana. The applicant's project report indicates that the development will consist of 10 residential blocks and one amenities block, providing a total of 2,057 units. This is an amendment to a previously granted environmental clearance that originally proposed 2,246 units.
The project includes the following building components:
| Block | No. of Blocks | Floors | Total Units | Built-up Area (sq. m) |
|---|---|---|---|---|
| Block A1 | 1 | 2C+G+9 | 277 | 19,820.8 |
| Block A2 | 1 | 2C+G+9 | 277 | 19,820.8 |
| Block A3 | 1 | 2C+G+9 | 277 | 19,820.8 |
| Block A4 | 1 | 2C+G+9 | 277 | 19,820.8 |
| Block B | 1 | 2C+S+12 | 144 | 22,285.5 |
| Block C1 | 1 | 2C+G+9 | 219 | 20,981.7 |
| Block C2 | 1 | 2C+G+9 | 219 | 20,982.0 |
| Block D | 1 | 2C+G+9 | 176 | 16,643.2 |
| Block E | 1 | 2C+G+9 | 119 | 12,409.9 |
| Block (LIG & EWS) | 1 | 2C+S+12 | 72 | 8,156.6 |
| Amenities Block | 1 | C+G+6 | - | 4,367.4 |
| Total | 11 | Max 13 floors | 2,057 | 2,55,113.5 |
Layout and design
The site layout is designed with a net plot area of 49,916.9 square metres after accounting for 1,619.1 square metres for road widening. The design incorporates 5,407.6 square metres of green area and 15,708.7 square metres for roads.
Parking is planned across two cellar floors and a stilt floor, providing space for 1,898 four-wheelers and 440 two-wheelers. The circulation plan includes a 7-metre wide ground floor driveway, 5-metre wide cellar driveways, and eight ramps with a 1 in 10 slope. A total of 44 lifts are planned, each with a capacity of 20 to 24 passengers.
Land and surroundings
The project site is located at Survey Nos. 663(P), 667, 668(P), and 671(P) in Kapra Village. It is bordered by open land to the east and existing residential buildings to the south and west. Access is provided by an existing 18-metre wide road connecting to Bank Colony. The nearest railway station is Cherlapalli, located 6.17 km away. The applicant notes that the site is in a sloping, rolling terrain, which will require significant cut and fill operations involving approximately 59,900 cubic metres of cutting and 47,920 cubic metres of filling.
Water, power and access
During the occupation stage, the total water requirement is estimated at 1,496.4 kilolitres per day (KLD). The applicant proposes to draw 971.9 KLD of fresh water from the Hyderabad Metropolitan Water Supply and Sewerage Board (HMWSSB). The remaining 524.5 KLD will be met through recycled treated wastewater used for flushing. A Sewage Treatment Plant (STP) with a capacity of 1,500 KLD, using Sequential Batch Reactor (SBR) technology, will be installed.
Power requirement for the project is estimated at a maximum demand of 11,335 kVA, to be drawn from TSTRANSCO. For emergency backup, 20 diesel generator (DG) sets of 500 kVA each are proposed. Solar energy will be utilized for external lighting and fencing, with an estimated saving of 12.26 lakh units per year.
Environmental safeguards
Solid waste generation is estimated at 6,685 kg per day. The applicant plans to segregate waste at source into biodegradable (3,209 kg) and non-biodegradable categories. Biodegradable waste will be processed in an organic waste converter. For storm water management, 98 rainwater harvesting pits (1.5m x 1.5m x 2.0m) are proposed.
Construction and demolition waste is estimated at 12,755.7 tons over the five-year construction period. The applicant intends to reuse concrete and bricks for site leveling and road sub-base construction. To mitigate the urban heat island effect, the project will use paints with an albedo of at least 0.4 and provide cool or green roofs.
Timeline
The applicant's conceptual plan estimates a construction period of approximately 36 months. The workforce requirement during the peak construction phase is expected to be 200 people, with a total requirement of 10,000 man-days.
Residential Apartments Construction Project - Janapriya Engineers Syndicate Private Limited Located site plan and layout
4 drawings from the project's filings. Sign in free to see them.
🔒 Sign in free to see it
🔒 Sign in free to see it
🔒 Sign in free to see it
🔒 Sign in free to see itIn context
394 applications in Medchal Malkajgiri since January 2022 are in the same category (Buildings & townships): 300 approved, 54 filed or under review, and 40 withdrawn, lapsed or rejected. The approved ones took a median of 2 months from filing to approval. At 12.7 acres, this one is larger than 80% of them.
11 other applications of any kind have been filed within 5 km of this site since January 2022.
Where it is
Kapra, Medchal Malkajgiri, Telangana. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.
Other projects nearby
- Residential Apartments Construction Project - M/s. Janapriya Engineers… — cleared for impact study, 0 m away
- Building project by M/s Kranti Infra — environmental approval granted, 650 m away
- Residential Apartments Construction Project - E-INFRA KAPRA APARTMENT by Sri.… — environmental approval granted, 2.2 km away
- Amendment in Environmental Clearance for Construction of Proposed Residential… — lapsed, 2.3 km away
- Building project by M/s. ARD Estates and Projects Pvt Ltd — under environmental review, 2.4 km away
- Residential Apartments Construction Project for Active Senior Living - Omsree… — environmental approval granted, 3.7 km away
- Residential Apartments Construction Project for Active Senior Living - Omsree… — environmental approval granted, 3.7 km away
- Residential Apartments Construction Project by M/s. Devansh Infra Private… — environmental approval granted, 4.2 km away
About this information
This page is compiled from publicly available approval records and rewritten in plain language. Statuses can change between our updates, so check with the authority before making decisions. Spotted a mistake? Tell us.