| Status | Cleared for impact study |
|---|---|
| Status since | 23 Feb 2023 |
| Application filed | 23 Feb 2023 |
| Approval sought | Environmental approval |
| Application type | Early planning |
| Sector | Industry |
| Applicant | Arun Vyapar Udyog Private Limited |
| Land area | 3.7 acres (1.5 ha) |
| Project cost | ₹30.2 crore |
| Village / locality | Pappankuppam |
| Taluk / tehsil | Gummidipoondi |
| District | Thiruvallur |
| State | Tamil Nadu |
| Location from | Site boundary on record |
| Our reference | WID-TN-00215 |
All filings for this project
This project has 2 applications on record. Each is a separate step (an impact study, an approval, an expansion…):
| Filing | Status | Land | Cost |
|---|---|---|---|
| New project filed 24 Mar 2023 | Application filed | 3.7 acres | ₹30.2 crore |
| Early planning filed 23 Feb 2023 (this page) | Cleared for impact study | 3.7 acres | ₹30.2 crore |
In context
56 applications in Thiruvallur since January 2022 are in the same category (Industry): 32 approved, 19 filed or under review, and 5 withdrawn, lapsed or rejected. The approved ones took a median of 2 months from filing to approval. At 3.7 acres, this one is smaller than 91% of them.
34 other applications of any kind have been filed within 5 km of this site since January 2022.
Where it is
Pappankuppam, Gummidipoondi, Thiruvallur, Tamil Nadu. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.
Other projects nearby
- Existing Steel rolling mill by M/s. Arun Vyapar Udyog Pvt Ltd — application filed, 0 m away
- Proposed Modification in Induction Furnace Configuration by increasing the… — initial checks, 150 m away
- Expansion of Existing Billets manufacturing facility from 26,000 Tons per… — lapsed, 250 m away
- Expansion of Existing Billets manufacturing facility from 26,000 Tons per… — more information requested, 250 m away
- Expansion of Existing Billets manufacturing facility from 26,000 Tons per… — cleared for impact study, 250 m away
- Proposed Expansion of Steel Rolling Mill & inclusion of Steel Melting Shop in… — more information requested, 450 m away
- Proposed Expansion of Steel Rolling Mill & inclusion of Steel Melting Shop in… — cleared for impact study, 450 m away
- Proposed Expansion of Steel Rolling Mill & inclusion of Steel Melting Shop in… — under wildlife review, 450 m away
About this information
This page is compiled from publicly available approval records and rewritten in plain language. Statuses can change between our updates, so check with the authority before making decisions. Spotted a mistake? Tell us.